Distribution of Stakeholder Analysis outcome and Stakeholder register

linkedin twitter facebook  
avatar
Mohammad Khan Deputy Vice President, Program Management| MetLife Bangladesh Dhaka, Bangladesh
Stakeholder analysis is performed by project manager/project team using different tools and techniques. During the analysis there might be some finding about some stakeholders that might hurt them if revealed. So as per PMI standards, what is recommended about distribution of stakeholder analysis outcome and stakeholder register among the same/all stakeholders?
Sort By:
avatar
Luis Branco CEO| Business Insight, Consultores de Gestão, Ldª Carcavelos, Lisboa, Portugal
Dear Mohammad
Interesting your question
Thanks for sharing

Stakeholder analysis is on "Influence", "Power" and "Interest" regarding the project
The objective is to define the best communication strategy for your involvement in the project.

I would like to understand better: "During the analysis there might be some finding about some stakeholders that might hurt them if revealed"
...
1 reply by Mohammad Khan
Dec 11, 2019 12:13 PM
Mohammad Khan
...
During the analysis the project team might find one stakeholder is resistant although the stakeholder thinks himself supportive of the project. If this outcome is shared with that stakeholder, he might not take it sportingly. This is one of the example of what I meant.
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
It depends on the organizational cultre, at least in my personal experience. For example, in my actual work place, stakehodler anaysis is published and it is a document that must be agreed and signed off as part of our governance process. If a result for a stakeholder is not what it could be or something like that in my actual work place it is taken as an opportunity to work with the stakeholder to help of project goal achievement.
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Mohammad -

Given the subjective nature of what is in the stakeholder register and the potential issues which could arise if certain (especially external) stakeholders learn its contents, I've often seen only specific content within it being shared with key stakeholders.

Kiron
avatar
Abolfazl Yousefi Darestani Manager, Quality and Continuous Improvement| Hörmann-TNR Industrial Doors Newmarket, Ontario, Canada
it depends. However, I do agree with Kiron.
avatar
Mohammad Khan Deputy Vice President, Program Management| MetLife Bangladesh Dhaka, Bangladesh
Dec 11, 2019 4:07 AM
Replying to Luis Branco
...
Dear Mohammad
Interesting your question
Thanks for sharing

Stakeholder analysis is on "Influence", "Power" and "Interest" regarding the project
The objective is to define the best communication strategy for your involvement in the project.

I would like to understand better: "During the analysis there might be some finding about some stakeholders that might hurt them if revealed"
During the analysis the project team might find one stakeholder is resistant although the stakeholder thinks himself supportive of the project. If this outcome is shared with that stakeholder, he might not take it sportingly. This is one of the example of what I meant.