Project Management

Please login or join to subscribe to this thread

Managing Project and Contract Management

linkedin twitter facebook   Construction   Organizational Project Management   Procurement Management  
avatar
Mushtaq Abdulrahimzai SWIS| Surrey Schools District 36 Toronto, Ontario, Canada
I am newly hired as PM for a DAM project, the project is a delay for about 3 years, still, the contractor is trying to delay the project as the project is 80% completed, what to do in such case, please share your experience.
Sort By:
< 1 2 3 >
avatar
Mushtaq Abdulrahimzai SWIS| Surrey Schools District 36 Toronto, Ontario, Canada
Jan 23, 2020 8:35 AM
Replying to Vincent Guerard
...
Ahmad,

A Dam is a large construction project. Adding to Sergio comments, you need to see the contract with that contractor, get all change regarding that contract. Analyze what did append, what side is the cause for what. I currently completing a similar analysis for the office of the auditor general.
Thank you, great information, i am sure this will help me
avatar
Mushtaq Abdulrahimzai SWIS| Surrey Schools District 36 Toronto, Ontario, Canada
Jan 23, 2020 10:10 AM
Replying to Peter Rapin
...
The key is in your title - Contract Management. To manage the contract you have to know the contract and the history of the contract. Does the contract remain enforceable? Have past decisions and acceptance essentially voided the terms of the contract? Has the owner caused the delays and how were those delays recognized? Have there been delay claims? Have there been requests for extensions (and approvals)? Has the initial scope changed?
You have essentially two options: 1) try to get the contract back on the rails through enforcement, or 2) start with a new slate - put the project past behind and start anew from where you are, renegotiate the contract to reflect the new reality and go forward. My guess is that either way its going to cost a tonne of money and considerable effort. Good luck.
avatar
Peter Rapin Subject Matter Expect; Project Delivery| Independent Consultant Ontario, Canada
Jan 23, 2020 10:40 AM
Replying to Mushtaq Abdulrahimzai
...
Noted and yeah they think more delays will pay them more which is mot possible
When you say "... is not possible", is it not possible because of the terms of the contract OR because funding is limited? The contract rules. Unless there is a specific condition in the contract that ties it to available funding the contractor can and will submit claims which will be successful if validated regardless of funding limitations. "I have no money" is not a recognized defense.
...
1 reply by Mushtaq Abdulrahimzai
Jan 25, 2020 12:55 AM
Mushtaq Abdulrahimzai
...
Sir, what I want to mentioned that I will try and will work with all stakeholders to not pay them more as it is a fixed price contract.
avatar
Mushtaq Abdulrahimzai SWIS| Surrey Schools District 36 Toronto, Ontario, Canada
Jan 23, 2020 10:10 AM
Replying to Peter Rapin
...
The key is in your title - Contract Management. To manage the contract you have to know the contract and the history of the contract. Does the contract remain enforceable? Have past decisions and acceptance essentially voided the terms of the contract? Has the owner caused the delays and how were those delays recognized? Have there been delay claims? Have there been requests for extensions (and approvals)? Has the initial scope changed?
You have essentially two options: 1) try to get the contract back on the rails through enforcement, or 2) start with a new slate - put the project past behind and start anew from where you are, renegotiate the contract to reflect the new reality and go forward. My guess is that either way its going to cost a tonne of money and considerable effort. Good luck.
Thank you for giving such useful information, i noted all of them and will work on them
avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
Jan 23, 2020 10:40 AM
Replying to Mushtaq Abdulrahimzai
...
Noted and yeah they think more delays will pay them more which is mot possible
Is the contract time and material?
You need to see if they have contractual conditions to increase your cost for the same work in more time.
...
1 reply by Mushtaq Abdulrahimzai
Jan 25, 2020 12:56 AM
Mushtaq Abdulrahimzai
...
it is a fixed price contract, but they are insisting that there are some activities they are doing or they did before which was not part of this contract.
avatar
Deepesh Rammoorthy ICT Project Manager ( PMP®AgilePM®Certified ScrumMaster® (CSM®))| Australian Red Cross Blood Service Tarneit, Vic, Australia
hi Ahmad

I would suggest get a member of your Legal and Procurement team to look at this contract terms and conditions in minute details and see how you can address the contractor issue.

If your legal team says that the contractor is entitled to extra money to finish the work , you then need to approach your sponsor to release the additional funds and help complete the project.

You may not be able to do a lot of Forensic work on what went wrong and why the delay and it is not suggested to use up your valuable time in doing so. It is now important for you to complete the project and close this contract.

It may end up being a meeting between you , the legal and procurement team and this contractor to try and arbitrate and resolve the issue .

If arbitration or negotiation does not resolve it , a formal letter of dispute resolution from your legal team to this contractor may be the way to go.
...
1 reply by Mushtaq Abdulrahimzai
Jan 25, 2020 12:58 AM
Mushtaq Abdulrahimzai
...
Thank you Deepesh Rammorthy, thank you for the valuable information.
avatar
Mushtaq Abdulrahimzai SWIS| Surrey Schools District 36 Toronto, Ontario, Canada
Jan 23, 2020 11:02 AM
Replying to Peter Rapin
...
When you say "... is not possible", is it not possible because of the terms of the contract OR because funding is limited? The contract rules. Unless there is a specific condition in the contract that ties it to available funding the contractor can and will submit claims which will be successful if validated regardless of funding limitations. "I have no money" is not a recognized defense.
Sir, what I want to mentioned that I will try and will work with all stakeholders to not pay them more as it is a fixed price contract.
avatar
Mushtaq Abdulrahimzai SWIS| Surrey Schools District 36 Toronto, Ontario, Canada
Jan 23, 2020 11:47 AM
Replying to Vincent Guerard
...
Is the contract time and material?
You need to see if they have contractual conditions to increase your cost for the same work in more time.
it is a fixed price contract, but they are insisting that there are some activities they are doing or they did before which was not part of this contract.
...
1 reply by Peter Rapin
Jan 25, 2020 10:17 AM
Peter Rapin
...
As a contractor many moons ago my response to clients that advised me there was no additional moneys (no appetite for change orders) was: "then don't ask me to do work that is over and above the initial scope. You, as the client, are the only ones that can control scope growth which invariably results in additional expenditures, extension in contract duration and billings."
Yes, you could be stuck with a unethical contractor, however the most likely scenario is that the client has/had an active role in the current situation. Look inward as well as outward.
avatar
Mushtaq Abdulrahimzai SWIS| Surrey Schools District 36 Toronto, Ontario, Canada
Jan 23, 2020 9:38 PM
Replying to Deepesh Rammoorthy
...
hi Ahmad

I would suggest get a member of your Legal and Procurement team to look at this contract terms and conditions in minute details and see how you can address the contractor issue.

If your legal team says that the contractor is entitled to extra money to finish the work , you then need to approach your sponsor to release the additional funds and help complete the project.

You may not be able to do a lot of Forensic work on what went wrong and why the delay and it is not suggested to use up your valuable time in doing so. It is now important for you to complete the project and close this contract.

It may end up being a meeting between you , the legal and procurement team and this contractor to try and arbitrate and resolve the issue .

If arbitration or negotiation does not resolve it , a formal letter of dispute resolution from your legal team to this contractor may be the way to go.
Thank you Deepesh Rammorthy, thank you for the valuable information.
avatar
Luis Branco CEO| Business Insight, Consultores de Gestão, Ldª Carcavelos, Lisboa, Portugal
Dear Ahmad
Interesting your question
Thanks for sharing

I have been carefully reading the answers given to you
I am convinced that, once you have them, you will find the best solution to resolve this situation
I wish you a great success
< 1 2 3 >

Please login or join to reply

Content ID:
ADVERTISEMENTS
ADVERTISEMENT

Sponsors