Preparing a resource mangement/utilization report

linkedin twitter facebook  
avatar
Shahriar Khondokar Project Manager| GraphicPeople Dhaka, Bangladesh
I work in a software company where every week we produce a resource utilization report for the next 4-week period.
The purpose of this report is to document how the 40 resources (which includes Developers, Quality Assurance Engineers, Development/Network Managers) will be spending their time in the current and upcoming projects. Ideally, we will also want to generate various summary data at the end of the report.
I was wondering if:
1. any one can provide any tips on preparing such a report.
2. there is any Excel spreadsheet/template that i can use and is available for free to aid with this purpose. Any free desktop tool similar to an Excel spreadsheet is welcome too.
Sort By:
avatar
Elyse Nielsen Senior Project Manager| Ascension Health Information Services Haines City, Fl, United States
Hi,

Here are some lessons learned, from my previous experience. Hopefully, these lessons will be of use to you.


  • Have a Standardized Time Reporting Categories - Assures you are reporting apples to apples. For example, project meetings are project time categories, not administration.

  • Have a couple of different rollup categories - perhaps by time spent in Break/Fix, Project Work, etc..., by Team, by Project, by Individual.

  • Have a way to display scheduling conflicts for resources across all needed project work.

  • Have a comparison which displays what was predicted as need versus what was utilized.



Good Luck!
Elyse
http://www.anticlue.net
avatar
Andrew Makar Program Manager| AMAKAR LLC Oakland Township, Mi, United States
Hi Shariar -

I had the exact same problem before and I solved it by creating a resource management model in MS Project. The ideas was to build a model with monthly forecasts to get an approximation of work so we could measure the capacity in the pipeline.

This article will show you how to get started:
Meet the Resource Management Model

Thanks!

Andy Makar
http://www.tacticalprojectmanagement.com
Deliver better with our MS Project Tutorial and Project Status Report techniques!
...
2 replies by Kevin Tukei and Minaketan Dash
Feb 28, 2017 1:44 AM
Minaketan Dash
...
Can I compare the ROI method by dividing the total revenue of project with total required effort? Also I 'll take the utilization percentage per resource weekly. One parameter will be the investment the Project sponsor is doing will be a constant . If we can utilize the daily effort of the employee for multiple task in an effective way, we can maximize the ROI% from a resource remaining the investment constant.
May 24, 2018 2:41 PM
Kevin Tukei
...
Hi Andrew,

Looks like the link you shared is broken. Can you please re-post if possible?
avatar
Minaketan Dash Cloud Engineering Project Manager. (PMP, MSP, PRINCE2, CSM)| Oracle Noida, India
I am also facing this challenges, Can anyone please share his/her format for resource utilization mapping?
avatar
Minaketan Dash Cloud Engineering Project Manager. (PMP, MSP, PRINCE2, CSM)| Oracle Noida, India
Dec 01, 2009 12:33 PM
Replying to Andrew Makar
...
Hi Shariar -

I had the exact same problem before and I solved it by creating a resource management model in MS Project. The ideas was to build a model with monthly forecasts to get an approximation of work so we could measure the capacity in the pipeline.

This article will show you how to get started:
Meet the Resource Management Model

Thanks!

Andy Makar
http://www.tacticalprojectmanagement.com
Deliver better with our MS Project Tutorial and Project Status Report techniques!
Can I compare the ROI method by dividing the total revenue of project with total required effort? Also I 'll take the utilization percentage per resource weekly. One parameter will be the investment the Project sponsor is doing will be a constant . If we can utilize the daily effort of the employee for multiple task in an effective way, we can maximize the ROI% from a resource remaining the investment constant.
avatar
Kevin Tukei Project Manager, PMP, CSM Burtonsville, Md, United States
Dec 01, 2009 12:33 PM
Replying to Andrew Makar
...
Hi Shariar -

I had the exact same problem before and I solved it by creating a resource management model in MS Project. The ideas was to build a model with monthly forecasts to get an approximation of work so we could measure the capacity in the pipeline.

This article will show you how to get started:
Meet the Resource Management Model

Thanks!

Andy Makar
http://www.tacticalprojectmanagement.com
Deliver better with our MS Project Tutorial and Project Status Report techniques!
Hi Andrew,

Looks like the link you shared is broken. Can you please re-post if possible?

Please login or join to reply

Content ID:
ADVERTISEMENTS

"The face of a child can say it all, especially the mouth part of the face."

- Jack Handey

ADVERTISEMENT

Sponsors