Why is Management reserve is not included in schedule baseline? PMBOK 6th edition page202 Saving Changes...
Sort By:
Luis BrancoCEO| Business Insight, Consultores de Gestão, LdªCarcavelos, Lisboa, Portugal
Dear HENDRY
Interesting your question
Thanks for sharing
Management reserves are created and managed by management
For this reason, they do not integrate in schedule baseline Saving Changes...
Sergio Luis ConteHelping to create solutions for everyone| Worldwide based OrganizationsBuenos Aires, Argentina
Is out of it. Is an amount the project manager can manage without justify it "physically". I meant, the project manager must not show a receipt to justifify the cost of something, for example. Saving Changes...