You have been given a project to build a park for a local community. Currently you are developing approaches to involve project stakeholders based on their needs, expectations, interests, and potential impact on the project. Which of the following is not an output of this process?
(a) Communication management plan
(b) Risk register
(c) Stakeholder register
(d) None of the above Saving Changes...
Thomas WalentaGlobal Project Economy ExpertHackenheim, Germany
The process described is 'plan stakeholder engagement' and the only output of it the stakeholder engagement plan. Hence the right answer is d.
a,b, and c are all outputs of the identify stakeholders process, some on 2nd level. Saving Changes...