Control schedule

linkedin twitter facebook  
avatar
HENDRY CHARLES.A Additional Chief Engineer| BANGALORE METRO RAIL CORPORATION LTD Thillai Nagar,Managiri, Tamil Nadu, India
What is the necessity of considering scope baseline as a INPUT to control schedule ?PMBOK ,page 222
Sort By:
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Activities defined in the schedule baseline trace back to work packages within the WBS which is part of the scope baseline. Sometimes, we may need to report on progress at the work package or control account level - if the schedule does not explicitly show this linkage, you'd have to go back to the scope baseline.
avatar
MD Sarfaraj Alam Advisor, Sales Operations| Dell Technologies India
Thanks for your question, Hendry.

WBS is a direct feed to schedule planning. Elements of WBS decide the schedule (the more the WBS elements, the longer the schedule). This is referred to periodically while keeping schedule in check. Schedule variance will be impacted if the project digresses from the approved scope baseline (WBS).
avatar
SHADAV MOHAMMAD ANSARI PMO| ITC INFOTECH INDIA PVT. Ltd. New Delhi, Delhi, India
Scope baseline is referred to as the approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed only through formal change control procedures and is used as a basis for comparison. In control schedule process , you need to monitor the status of activities related to a particular project. Aside from monitoring the status, it also involves updating of the project process as well as managing the changes to the schedule in order to achieve the plan.
avatar
Evgeniy Sychugov Project Manager| Gazprom Neft Saint-Petrsburg, Russian Federation
Milestones should be defined correctly and often. On each milestone schedule plannig should be replaned and decision about changing schedule must be confirmed if its needs.
Important to note, if different changes on other planning stages makes changes in scope or budget schedule must be reviewed. It couldn't stays without changes.
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Because the components of the scope baseline.
avatar
Steve Ratkaj Ontario, Canada
1. Your schedule must include all project scope.
2. Baselining your schedule then implies baselining your scope.
3. Any "new" scope (intended or forgotten) needs to added to the schedule, and then perhaps rebaselined.
avatar
Abolfazl Yousefi Darestani Manager, Quality and Continuous Improvement| Hörmann-TNR Industrial Doors Newmarket, Ontario, Canada
I agree with Kiron.