how to calculate the Task progress in (%) using efforts

linkedin twitter facebook  
avatar
Gopal Mahalingam Engineering Manager| Robert Bosch Engineering and Business Solutions Ltd Coimbatore, Tamilnadu, India
Currently i am in design phase . I want to calculate the Task progress in (%) using efforts spent .
Sort By:
avatar
bhawani mittal Project Manager| Alcatel-Lucent Delhi, Delhi, India
There is no straight rule, you need to use earned value analysis. You need to break down your work(i.e. design) in different parts and then define how much each part contributes in overall work. Once these sub parts are completed, you will come to know that how much has been completed.
avatar
Gopal Mahalingam Engineering Manager| Robert Bosch Engineering and Business Solutions Ltd Coimbatore, Tamilnadu, India
Hi Bhawani,

Thanks for your clarification. Because of the new product development activity, initially i don't have any concrete data, such as so many SLOC/ELOC approx.
I will try to follow your suggestion by breaking in to small modules , Also i have started using EVA.

Have a nice day..