Your project management plan results in a project schedule that is too long If the project network diagram cannot change but you have extra personnel resources, what is the BEST thing to do? A-) Fa
In the real world the answer would be "it depends" but academically, if you have extra resources and some of the activities along the critical path(s) are effort driven then crashing the schedule would be the choice they are guiding you to. Saving Changes...