MS Project assignment question

linkedin twitter facebook  
avatar
Rick Graham Director| Benchmark Skills Ltd Matlock, Derbyshire, United Kingdom
I have 1 full time and 1 part-time resource (just works Tuesdays). I have a 1 day task which both resources must work on together. Is there a way of setting this up so that I can assign both resources and they both work on the day constrained by the part-time resource?
I want to avoid manual workaround. I'm using 2003, but can use 2007 if needed.
Thanks in advance!
avatar
Hans Robbers Senior Director| Salesforce Vlissingen, Netherlands
Rick

One way is to set up the personal calender for the part time resource that only Tuesday is a working day. Assign both to the task which will than appear on Tuesday.
Another way is to fix the task to Tuesdays by creating a repeasting task with a duration of 1 day effort of 16 hours assign the resources to it and end date always on the Tuesday

Hopes this helps
Hans