Who should PM escalate to if team resource being used in other project in the exam?

linkedin twitter facebook  
avatar
Tin Ming Lam Project Manager| Dyson Hong Kong, 852, Hong Kong
I saw some exam questions asking this, but I can't find the answer.

Thanks.
Sort By:
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Start by talking with the team member but if they are unable/unwilling to change this behavior, speak with their people/functional manager if you are in a matrix or functional organization structure.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Tin

Escalation could be in response to a negative risk or to a situation. Whom and how to escalate depends on two things:

1) The situation and context.
2) The escalation plan and governance structure.

Sometimes you need to escalate to the sponsor if it exceeds your authority or to other relevant part of the organization.