Apr 11, 2020 3:21 PM
Replying to NIKHIL VIDWANS
...
I think it is important to consider the circumstances in which the project reached this situation. I tend to think such a situation is possible probably because of an Act of God. If that was indeed the case, the project can be recovered with fresh baselines and CCB approvals. Most contracts would have the Force Majeure clause.
On the other hand, it would be very difficult to retrieve the project if several initial indications of baseline variations were missed or any acts of omission or commission were subsequebtly detected. This would most likely severely shake the customer's faith in the project team's ability to deliver. In this case, I suppose a negotiated project closure may be the only way ahead - alongwith considerable reputation costs. A very unfortunate situation indeed.