Apr 13, 2020 10:56 AM
Replying to Thomas Walenta
...
Riad,
if it is part of the approved scope and even the contract, the contractor owes it. Sometimes a contract provision is part of the product (the WHAT) and sometimes it is rather a requirement HOW to achieve the what. And this is sometimes regulated (does UAE require BIM in construction projects?). If it is regulated, the contractor must do it, not only for you but for government,
While you say the project process is OK in the moment, maybe future progress and future maintenance might be hampered without the automation, so there is a risk even beyond the project.
I would try to understand why the contractor does not fulfill this requirement and demand it formally.