ibrahim zahran Sr. Projects Engineer| Nalco Saudi Arabia Saudi Arabia
Can anyone please help me to understand the difference between the Time-Scaled Schedule Network Diagram (also called logic bar chart) and the Time-Scaled Logic Diagram, the PMBOK 6th edition in p.218 has falid to explian the difference clearly ?
Sort By:
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Ibrahim -

The former has all activities on separate rows whereas the latter will have activities related to similar deliverables, control accounts or other "higher" WBS nodes on the same row.

If you Google for "Time-scaled logic diagram" you will see examples created in Primavera P6.

It's just a different method of visualizing the same content...

Kiron
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Time Scaled Schedule Network is a barchar. Lenght of the bar represent the activity duration. There is no relation between the activities, Just bars that shown the activities duration. Time-Scaled Logic Diagram is a barchar with activity relations into it. For example arrows will link bars to show activity relations.
avatar
Abolfazl Yousefi Darestani Manager, Quality and Continuous Improvement| Hörmann-TNR Industrial Doors Newmarket, Ontario, Canada
Sergio made a good point