Project Management

Please login or join to subscribe to this thread

You are managing a $10 million project. Which of the following is an acceptable cause for "re-baselining" this project? A. The client has approved an addition to the scope of the project wit

linkedin twitter facebook   Integration Management  
avatar
yazeed khairudein Riyadh, Saudi Arabia
You are managing a $10 million project. Which of the following is an acceptable cause for "re-baselining" this project?
A. The client has approved an addition to the scope of the project with a $150,000 budget increase and a two-week extension of the scheduled completion.
www.alsenosy.com | www.professionalengineers.us
B. The contractor’s company has instituted a quality assurance program in which it has pledged to spend $1 million during the next year.
C. The productivity in the design department is lower than estimated, which has resulted in 1,000 additional hours over what was budgeted and a forecasted two-week delay of the scheduled completion.
D. The engineering department of the performing organization has converted to a new $250,000 CAD system.
Sort By:
< 1 2 >
avatar
Keith Novak Tukwila, Wa, United States
Not enough information.
A) 1.5% cost increase is relatively small and 2 weeks on top of how long a project?
B) There is nothing to say how the QA program impacts the project and whether the $1M is only on this project.
C) Similar to A. What is the burdened labor rate?
D) What is the impact of the CAD system on the project?
avatar
Khai Ng. IT PMO | IT Project Manager| TTGROUP Hanoi, Viet Nam
A) Client's approval has affected cost and time of the project, so it is a acceptable cause for rebaselining.
B) No information about the spending will affect project's scope, time, and cost.
C) No information about the delay will affect project time's time and cost. It does not tell whether the delayed work is on the critical path or not.
D) It does not tell the affect of the new system on the project.
avatar
Thomas Walenta Global Project Economy Expert Hackenheim, Germany
A
baselines are cost and schedule and these change with the approved change.
...
1 reply by Keith Novak
May 17, 2020 1:09 PM
Keith Novak
...
I disagree to some extent. Baselines reflect cost and schedule, but on a large project, it would be unwise to reset the entire cost and/or schedule baseline for every minor change. The administrative overhead for doing so would be more expensive than the changes themselves.

Changes where the schedule slide is less than the float don't require reconciling the Tier 0 schedule. Smaller changes can be collected for scheduled baseline blockpoints where they can be committed at the same time and the change management overhead can be shared rather than updating the baseline for each change. Otherwise you can get into a situation where by the time you have committed some minor change, some newer change has aldready superseded it so there is no firm baseline to align everyone's plans. You wind up in a constant state of churn.

Do the smaller changes need to be reflected in the next baseline update? Absolutely.

Does each change drive an update to the baseline? In many cases absolutely not.
avatar
Keith Novak Tukwila, Wa, United States
May 16, 2020 4:52 AM
Replying to Thomas Walenta
...
A
baselines are cost and schedule and these change with the approved change.
I disagree to some extent. Baselines reflect cost and schedule, but on a large project, it would be unwise to reset the entire cost and/or schedule baseline for every minor change. The administrative overhead for doing so would be more expensive than the changes themselves.

Changes where the schedule slide is less than the float don't require reconciling the Tier 0 schedule. Smaller changes can be collected for scheduled baseline blockpoints where they can be committed at the same time and the change management overhead can be shared rather than updating the baseline for each change. Otherwise you can get into a situation where by the time you have committed some minor change, some newer change has aldready superseded it so there is no firm baseline to align everyone's plans. You wind up in a constant state of churn.

Do the smaller changes need to be reflected in the next baseline update? Absolutely.

Does each change drive an update to the baseline? In many cases absolutely not.
avatar
David Portas London, United Kingdom
I would want to understand first why the baseline was justified and what it was for. Where baselines are used it surely makes sense to discard them as quickly as possible because stale forecasts are almost by definition going to be a very poor measure of success.
avatar
Thomas Walenta Global Project Economy Expert Hackenheim, Germany
Keith

true that relatively small changes in reality do not trigger rebaselining. Their consequences can be covered by corrective actions or contingencies.

In the given case of this question A is the only answer which somehow reflects on the question.

Besides, the client already approved the change, so now not to reflect this approval in the plan would be a unforced error.

And a delay of the project end date always should be shown in the schedule.
avatar
Peter Rapin Subject Matter Expect; Project Delivery| Independent Consultant Ontario, Canada
In my mind the Baseline is not a tracking tool. It should represent the initial objectives and constraints applied to the project, and agreed to."Re-baselining" should really be tied in to a revised Project Charter.

When comparing the actual performance to the 'baseline' a scope or constraint change would be used as a reason for a deviation. However, a "re-baseling" basically makes the baseline a tracking tool.

Another consideration here - when "re-baselining" does one apply only the authorized changes or do we include for performance to date? For example: if the schedule has slipped one month AND there is a two-week extension due to a scope change does the revised baseline show a six-week schedule extension? If so, when and if we recover some time, do we baseline again.

Save yourself the headache and only 're-baseline' with a Charter update! Preferably, don't do either.
...
2 replies by Peter Rapin and Thomas Walenta
May 18, 2020 12:09 PM
Peter Rapin
...
As a clarification I totally ignored the multiple choice response and focused on my opinion of "re-baselining". Selecting A, B, C or D on my part would not have added anything. Managing a project is not the same as responding to test questions where answers are expected to be one-of-four. All such questions should have E "none of the above" AND/OR F "better choice would be ..."
May 18, 2020 2:19 PM
Thomas Walenta
...
Well, yes, everybody can manage, plan and track as they chose.

Baselines indeed are used as tracking tools, quote PMBoK 4.6.1.4:
'.. approved changes should be incorporated into a revised baseline'. Tools like MSP provide functionality to set a series of baselines over time.

And, as to another threat here, in my view the charter never changes, but the project management plan carries forward the progressive elaboration as well as substantial changes. I never had a change to a charter in 40 years.
avatar
Keith Novak Tukwila, Wa, United States
Thomas,
I agree in principle but I think it's a poorly worded question. I'll elaborate a bit because it may help others with test taking strategies, and some fundamental PM terminology...

When taking the PMP, you must often determine which is the best answer so as a test taker, asking what the question is specifically testing is a good strategy. In this case, it appears to be testing the understanding of a "baseline".

A baseline is the few critical items that form the basis for all other planning, such as the major milestones, and how much money is in different budget categories. I would generally say that if you move the end date, that would usually drive a replan of all impacted events, but in this case both A and C include a cost increase and 2 week completion delay. When taking a test, I'd conclude that can't be the deciding factor or both answers would be correct.

The only information about the project is that it's $10M, so there is really no way to evaluate whether the changes would have to be reflected in the lower level schedules or budget somewhere, or whether they are big enough that they could impact multiple lower level working plans, and would justify resetting the major milestones and top level budget, i.e. "the baseline". If there is float in the schedule or reserve in the budget, they may not, but when I read the question itself, there is no way to determine.
avatar
Peter Rapin Subject Matter Expect; Project Delivery| Independent Consultant Ontario, Canada
May 18, 2020 11:01 AM
Replying to Peter Rapin
...
In my mind the Baseline is not a tracking tool. It should represent the initial objectives and constraints applied to the project, and agreed to."Re-baselining" should really be tied in to a revised Project Charter.

When comparing the actual performance to the 'baseline' a scope or constraint change would be used as a reason for a deviation. However, a "re-baseling" basically makes the baseline a tracking tool.

Another consideration here - when "re-baselining" does one apply only the authorized changes or do we include for performance to date? For example: if the schedule has slipped one month AND there is a two-week extension due to a scope change does the revised baseline show a six-week schedule extension? If so, when and if we recover some time, do we baseline again.

Save yourself the headache and only 're-baseline' with a Charter update! Preferably, don't do either.
As a clarification I totally ignored the multiple choice response and focused on my opinion of "re-baselining". Selecting A, B, C or D on my part would not have added anything. Managing a project is not the same as responding to test questions where answers are expected to be one-of-four. All such questions should have E "none of the above" AND/OR F "better choice would be ..."
avatar
Thomas Walenta Global Project Economy Expert Hackenheim, Germany
May 18, 2020 11:01 AM
Replying to Peter Rapin
...
In my mind the Baseline is not a tracking tool. It should represent the initial objectives and constraints applied to the project, and agreed to."Re-baselining" should really be tied in to a revised Project Charter.

When comparing the actual performance to the 'baseline' a scope or constraint change would be used as a reason for a deviation. However, a "re-baseling" basically makes the baseline a tracking tool.

Another consideration here - when "re-baselining" does one apply only the authorized changes or do we include for performance to date? For example: if the schedule has slipped one month AND there is a two-week extension due to a scope change does the revised baseline show a six-week schedule extension? If so, when and if we recover some time, do we baseline again.

Save yourself the headache and only 're-baseline' with a Charter update! Preferably, don't do either.
Well, yes, everybody can manage, plan and track as they chose.

Baselines indeed are used as tracking tools, quote PMBoK 4.6.1.4:
'.. approved changes should be incorporated into a revised baseline'. Tools like MSP provide functionality to set a series of baselines over time.

And, as to another threat here, in my view the charter never changes, but the project management plan carries forward the progressive elaboration as well as substantial changes. I never had a change to a charter in 40 years.
< 1 2 >

Please login or join to reply

Content ID:
ADVERTISEMENTS

I see where one young boy has just passed 500 hours sitting in a treetop. There is a good deal of discussion as to what to do with a civilization that produces prodigies like that. Wouldn't it be a good idea to take his ladder away from him and leave him up there?

- Will Rogers

ADVERTISEMENT

Sponsors