Project Management

Please login or join to subscribe to this thread

PMP Exam Sample Question, What will be the answer?

linkedin twitter facebook  
avatar
Mushtaq Abdulrahimzai SWIS| Surrey Schools District 36 Toronto, Ontario, Canada
What are three processes used to begin an Agile project?

A-Iterations, Product Roadmap Planning, and Number of Sprint
Iterations

B-Visioning, Product Roadmap Planning, and Product Backlog
Definition

C-Visioning, Product Backlog Definition, and Project Charter Creation

D-Burndown chart, Product Roadmap, and sprints’ length
Sort By:
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
None of the above. There is no single way to be agile. Sprints, backlogs and use of tools like burn down charts are commonly used, but alternate approaches (e.g. lean Kanban) wouldn't require their usage...

Kiron
...
1 reply by Mushtaq Abdulrahimzai
Jun 23, 2020 12:40 AM
Mushtaq Abdulrahimzai
...
Dear Kiron, thank you.

i posted this question because, i was thinking the answer will be B, when i searched find three answers all of them were B, but PM Challenge question's answers was C, i took it is screen shot.

i face such problem more then 5 times.
avatar
Mushtaq Abdulrahimzai SWIS| Surrey Schools District 36 Toronto, Ontario, Canada
Jun 22, 2020 7:50 AM
Replying to Kiron Bondale
...
None of the above. There is no single way to be agile. Sprints, backlogs and use of tools like burn down charts are commonly used, but alternate approaches (e.g. lean Kanban) wouldn't require their usage...

Kiron
Dear Kiron, thank you.

i posted this question because, i was thinking the answer will be B, when i searched find three answers all of them were B, but PM Challenge question's answers was C, i took it is screen shot.

i face such problem more then 5 times.
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
I am really not a fan of the PM Challenge questions quality so I'm not surprised - stick to reputable (unfortunately paid) question pools, Ahmad!

Kiron
...
2 replies by Mushtaq Abdulrahimzai and Soha Karjawally
Jun 23, 2020 11:59 PM
Mushtaq Abdulrahimzai
...
Noted, and thank you so much.
Jun 24, 2020 2:23 AM
Soha Karjawally
...
Thanks, Kiron... I had doubts last time, then went back to Rita's book.
avatar
Mushtaq Abdulrahimzai SWIS| Surrey Schools District 36 Toronto, Ontario, Canada
Jun 23, 2020 8:42 AM
Replying to Kiron Bondale
...
I am really not a fan of the PM Challenge questions quality so I'm not surprised - stick to reputable (unfortunately paid) question pools, Ahmad!

Kiron
Noted, and thank you so much.
avatar
Soha Karjawally Software development manager / Program Manager| Phoenix - USA Montréal, Quebec, Canada
Jun 23, 2020 8:42 AM
Replying to Kiron Bondale
...
I am really not a fan of the PM Challenge questions quality so I'm not surprised - stick to reputable (unfortunately paid) question pools, Ahmad!

Kiron
Thanks, Kiron... I had doubts last time, then went back to Rita's book.
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
The only reason I'd pick C would be that its the only one that mentions a charter, and for the exam you need to know that without the existence of an approved charter a project should not exist.
avatar
Michele Jones Director of PM/PMO & PMP Prep Instructor| Quality Computing Projects Inc. Mississauga, Ontario, Canada
I agree. I mentioned the many errors to PMI and they asked me what they were. I replied that I didn't want to do 1000 questions again to find them for them. They should review them themselves.