I got the following question in one of the sample exams :
During a status meeting, a stakeholder requests a new requirement that was previously unidentified. What should the project manager do?
Perform a risk analysis
or
Execute the Perform Integrated Change Control process
the simulator recommends the first while i think the correct is the second .