I have to resource a project basis a 24 hour day. I have 12 people with 6 working from 7am til 7pm, and then the other 6 working 2nd shift from 7pm to 7am. I finally got the working calendar figured out but now I am struggling to get the shifts to start when they are supposed to start. ie, when the first shift is to start a new day at 7am, the people aren't starting until the previous linked task is complete. Regardless of time of day. Saving Changes...
Rakesh TrivediSenior Project Manager| IT CompanyIndore, Mp, India
Littile confused, Can you please elaborate the exact problem. Also,let me know if you are using 24hrs Calender to modfied the Standard calender default timings. Saving Changes...