Project Management

Please login or join to subscribe to this thread

How reliable are the answers in Project management study hall ?

linkedin twitter facebook  
avatar
Bhavna Vanvari Pune, Maharashtra, India
Today’s Q of the day is : https://www.projectmanagement.com/studyHall/questionOfTheDay.cfm

Due to resource challenges, a technology vendor is late with a critical project deliverable. There is a 20 percent buffer in the budget for cost overruns. What should the project manager do next to mitigate this issue?
A. Replace the current vendor and ask the new vendor to send a contract.

B. Assess alternative vendors that can support project deliverables regardless of resource

C. Discuss the legal implications of this slippage with the vendor.

D. Accept the cost overrun and update the project schedule.

Answer is B.

According to me answer should be C , as PM should discuss with the vendor before proceeding to change the vendor. Ethically, vendor should know that PM may change vendor if he misses delivery.

Please can someone help me understand why B is better option than C
Sort By:
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
This is a pretty poor question - A & B are virtually the same as B would lead to A. There is no indication of a relationship between the deliverable timing and cost implications so D can be eliminated. I'd agree with you that C is the best of a poor set of choices - I don't know that I'd use the term "legal implications" though as it would be better to refer to the contract regarding schedule delays on key deliverables first and speak directly with the vendor.

Kiron
...
1 reply by Bhavna Vanvari
Aug 22, 2020 4:20 PM
Bhavna Vanvari
...
Thanks for explanation??
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
I couldn't agree more with Kiron's feedback. It is surprising to see such questions in the Study Hall but hey Kiron, maybe we are old school :-)
...
2 replies by Bhavna Vanvari and Kwiyuh Michael Wepngong
Aug 22, 2020 4:20 PM
Bhavna Vanvari
...
??
Aug 23, 2020 1:12 PM
Kwiyuh Michael Wepngong
...
Hi Bhavna,
Kiron is quite insightful and indicting too??... the contract that binds the vendor and the project manager. Ethically it's needful that the PM talks with the vendor and assess the situation before considering option B
avatar
Bhavna Vanvari Pune, Maharashtra, India
Aug 21, 2020 5:57 PM
Replying to Kiron Bondale
...
This is a pretty poor question - A & B are virtually the same as B would lead to A. There is no indication of a relationship between the deliverable timing and cost implications so D can be eliminated. I'd agree with you that C is the best of a poor set of choices - I don't know that I'd use the term "legal implications" though as it would be better to refer to the contract regarding schedule delays on key deliverables first and speak directly with the vendor.

Kiron
Thanks for explanation??
avatar
Bhavna Vanvari Pune, Maharashtra, India
Aug 21, 2020 9:06 PM
Replying to Rami Kaibni
...
I couldn't agree more with Kiron's feedback. It is surprising to see such questions in the Study Hall but hey Kiron, maybe we are old school :-)
??
avatar
Kwiyuh Michael Wepngong
Community Champion
Financial Management Specialist | US Peace Corps Yaounde, Centre, Cameroon
Aug 21, 2020 9:06 PM
Replying to Rami Kaibni
...
I couldn't agree more with Kiron's feedback. It is surprising to see such questions in the Study Hall but hey Kiron, maybe we are old school :-)
Hi Bhavna,
Kiron is quite insightful and indicting too??... the contract that binds the vendor and the project manager. Ethically it's needful that the PM talks with the vendor and assess the situation before considering option B
...
2 replies by Bhavna Vanvari and Tom Gill
Aug 23, 2020 7:45 PM
Bhavna Vanvari
...
Thanks
Sep 14, 2021 10:07 PM
Tom Gill
...
Agreed. The ethical considerations seem to be completely absent from the programmed answer.
avatar
Bhavna Vanvari Pune, Maharashtra, India
Aug 23, 2020 1:12 PM
Replying to Kwiyuh Michael Wepngong
...
Hi Bhavna,
Kiron is quite insightful and indicting too??... the contract that binds the vendor and the project manager. Ethically it's needful that the PM talks with the vendor and assess the situation before considering option B
Thanks
avatar
Tom Gill Manager, Brand Operations| Jewelers Mutual Tx, United States
Aug 23, 2020 1:12 PM
Replying to Kwiyuh Michael Wepngong
...
Hi Bhavna,
Kiron is quite insightful and indicting too??... the contract that binds the vendor and the project manager. Ethically it's needful that the PM talks with the vendor and assess the situation before considering option B
Agreed. The ethical considerations seem to be completely absent from the programmed answer.
avatar
Tom Gill Manager, Brand Operations| Jewelers Mutual Tx, United States
Bhavna, I'm preparing for my PMP exam. I'm having regular cognitive conflicts with Study Hall. Have you had difficulties with many other questions? It seems like a good tool to prepare, but if the questions aren't valid, it may actually make preparation more difficult.

Please login or join to reply

Content ID:
ADVERTISEMENTS

"Two roads diverged in a wood, and I... took the one less traveled by, and that has made all the difference."

- Robert Frost

ADVERTISEMENT

Sponsors