you are scheduling some of activities in your costruction project. you are desired to start working on landscaping three weeks before the furniture purchase. what do you call this?
it is float
it is lead
it is lag
it is FS+3
Sort By:
avatar
Neil Harkin Training Facilitator| Portach Mona Services Ltd Westhill, Aberdeenshire, United Kingdom
It's a lag

Relationship would be SS+3 weeks
...
1 reply by Ghada Asfour
Sep 25, 2020 11:27 AM
Ghada Asfour
...
Can you explain to me please
avatar
Ghada Asfour Riyadh, Saudi Arabia / Riyadh Region /Ri, Saudi Arabia
Sep 25, 2020 11:25 AM
Replying to Neil Harkin
...
It's a lag

Relationship would be SS+3 weeks
Can you explain to me please
avatar
Neil Harkin Training Facilitator| Portach Mona Services Ltd Westhill, Aberdeenshire, United Kingdom
There are three types of relationship between activities in your network of project activities, assuming you're using a precedence network.

1 FS Finish to Start.
This is the most common and is the default relationship type that MS Project or Primavera will apply if you link two activities together. The first activity must finish before the next activity can start.

2 FF Finish to Finish.
Both activities must finish at the same time.

3 SS Start to Start.
Both activities can start at the same time.

From the information you provided you will start Activity 1(landscaping) and then start Activity 2 (furniture purchase) three weeks later.

So, the logical link should be Start to Start with a lag or delay of 3 weeks

I hope that makes sense
...
1 reply by Ghada Asfour
Sep 25, 2020 12:13 PM
Ghada Asfour
...
Yes
Thank you ????
avatar
Ghada Asfour Riyadh, Saudi Arabia / Riyadh Region /Ri, Saudi Arabia
Sep 25, 2020 11:56 AM
Replying to Neil Harkin
...
There are three types of relationship between activities in your network of project activities, assuming you're using a precedence network.

1 FS Finish to Start.
This is the most common and is the default relationship type that MS Project or Primavera will apply if you link two activities together. The first activity must finish before the next activity can start.

2 FF Finish to Finish.
Both activities must finish at the same time.

3 SS Start to Start.
Both activities can start at the same time.

From the information you provided you will start Activity 1(landscaping) and then start Activity 2 (furniture purchase) three weeks later.

So, the logical link should be Start to Start with a lag or delay of 3 weeks

I hope that makes sense
Yes
Thank you ????

Please login or join to reply

Content ID:
ADVERTISEMENTS

"Clothes make the man. Naked people have little or no influence on society."

- Mark Twain

ADVERTISEMENT

Sponsors