Project Management

Please login or join to subscribe to this thread

After project charter

linkedin twitter facebook  
avatar
Anonymous
Which is the right answer?

A project manager has developed and just received sign-off the project charter.
What process is the the project manager likely to perform next?
A. Develop project management plan
B. Develop cost management plan
C. Identify stakeholders
D. Develop project charter
Sort By:
avatar
Ghada Asfour Riyadh, Saudi Arabia / Riyadh Region /Ri, Saudi Arabia
According to the Initiation process group after Project Charter approval the PM should start the identify stakeholders process.
According to the Integration Management the next is to Develop Project Management Plan.

But I think next step should be to identify stakeholders. Project charter contains the key stakeholders but PM must identify all stakeholders.
avatar
Keith Novak Tukwila, Wa, United States
The project management plan is the superset of all the other plans so B and C are a subset of A. Key stakeholders are included in the charter, and D is a nonsensical answer so I'd go with A.
...
1 reply by Ghada Asfour
Nov 14, 2020 7:30 PM
Ghada Asfour
...
But identifying stakeholders is done during initiation after project charter or in parallel with it.
I mean it comes before developing the plan.
avatar
Ghada Asfour Riyadh, Saudi Arabia / Riyadh Region /Ri, Saudi Arabia
Nov 14, 2020 7:17 PM
Replying to Keith Novak
...
The project management plan is the superset of all the other plans so B and C are a subset of A. Key stakeholders are included in the charter, and D is a nonsensical answer so I'd go with A.
But identifying stakeholders is done during initiation after project charter or in parallel with it.
I mean it comes before developing the plan.
...
1 reply by Keith Novak
Nov 15, 2020 5:35 PM
Keith Novak
...
What are you initiating if not the PM plan?
avatar
Ashish Bharti Technician| American Electric Power Lynchburg, Va, United States
A. Develop project management plan
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
This is not a great question as it furthers the perception that PMBOK processes are performed in a linear fashion. D is a pure throwaway answer which furthers my point that this question was likely from a poor quality practice exam.
avatar
Kwiyuh Michael Wepngong
Community Champion
Financial Management Specialist | US Peace Corps Yaounde, Centre, Cameroon
Option A is the most viable for me
avatar
Keith Novak Tukwila, Wa, United States
Nov 14, 2020 7:30 PM
Replying to Ghada Asfour
...
But identifying stakeholders is done during initiation after project charter or in parallel with it.
I mean it comes before developing the plan.
What are you initiating if not the PM plan?
...
1 reply by Ghada Asfour
Nov 15, 2020 6:14 PM
Ghada Asfour
...
Developing project management plan is done during planning process group but before planning PM should identify all stakeholders so that he can collect their requirements and manage their expectations during planning
avatar
Ghada Asfour Riyadh, Saudi Arabia / Riyadh Region /Ri, Saudi Arabia
Nov 15, 2020 5:35 PM
Replying to Keith Novak
...
What are you initiating if not the PM plan?
Developing project management plan is done during planning process group but before planning PM should identify all stakeholders so that he can collect their requirements and manage their expectations during planning
...
1 reply by Keith Novak
Nov 16, 2020 10:29 AM
Keith Novak
...
If you are identifying impacted people, you are planning. Again...the PMBOK is not a cook book. Those are knowledge areas and not sequential.

Believe what you wish however, and good luck with your exam.
avatar
Keith Novak Tukwila, Wa, United States
Nov 15, 2020 6:14 PM
Replying to Ghada Asfour
...
Developing project management plan is done during planning process group but before planning PM should identify all stakeholders so that he can collect their requirements and manage their expectations during planning
If you are identifying impacted people, you are planning. Again...the PMBOK is not a cook book. Those are knowledge areas and not sequential.

Believe what you wish however, and good luck with your exam.

Please login or join to reply

Content ID:
ADVERTISEMENTS

"Put your hand on a hot stove for a minute, and it seems like an hour. Sit with a pretty girl for an hour, and it seems like a minute. THAT's relativity."

- Albert Einstein

ADVERTISEMENT

Sponsors