Rita Mulcahy PMP Exam Prep Ninth Edition exercise question...

linkedin twitter facebook  
avatar
Lilian Seow Intracorp Projects Ltd. British Columbia, Canada
What is the AC answer for the question on page 301 of Rita Mulcahy PMP Exam Prep Ninth Edition? I got 3400 [1000+1200+600+600].
I tried reaching out to RMC and unfortunately, no response.
avatar
Thomas Walenta Global Project Economy Expert Hackenheim, Germany
Lilian,
if you refer to the question named 'the fence #2', why do you have 1200 in your sum? In my book, this AC part would be 900 (activity side 2), hence the sum AC = 3100.