Who is responsible for which project deliverables? Who are the stakeholders involved?

linkedin twitter facebook  
avatar
Mohd Azmirul Adha Azmir Project Manager| Buildserve Engineering Puchong, Selangor, Malaysia
Responsibility is primarily internal. Who owns what part of the project? Make sure your team serves your client’s needs by staying organized and clearly communicating responsibilities. TeamGantt’s free project management software makes it easy to assign tasks and track progress along the way.

Every project also has an owner. It might be the person you’re talking to. It might be that person’s boss. No matter what, you need to know who’s going to give you final approval—and who’s going to sign those checks. Be sure you loop the owner of the project in, and keep them informed at the right steps. It’s important to sort those details out before you start work.
Sort By:
avatar
Verónica Elizabeth Pozo Ruiz RYLAI Access Control Quito, Pichincha, Ecuador
A Responsibility Assignment Matrix (RAM) describes the participation by various organizations, people and roles in completing tasks or deliverables for a project. It's used by the Program Manager (PM) in clarifying roles and responsibilities in cross-functional team, projects and processes.
...
1 reply by Kwiyuh Michael Wepngong
Jan 07, 2021 5:13 AM
Kwiyuh Michael Wepngong
...
Perfectly stated,
Once this is missed, it gets tough
avatar
Kwiyuh Michael Wepngong
Community Champion
Financial Management Specialist | US Peace Corps Yaounde, Centre, Cameroon
Jan 06, 2021 11:44 PM
Replying to Verónica Elizabeth Pozo Ruiz
...
A Responsibility Assignment Matrix (RAM) describes the participation by various organizations, people and roles in completing tasks or deliverables for a project. It's used by the Program Manager (PM) in clarifying roles and responsibilities in cross-functional team, projects and processes.
Perfectly stated,
Once this is missed, it gets tough
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
First of all, my recommendation is not reinvent the wheel. There are well known, stablished and agreed things like RACI to answer your questions. With that said, the way you assign way of acting to each role is up to your company. Just as example, in the company where I am working on, because the company was not satisfying with the RASCI model we used, we create our own model (based on it) and it is unique no matter the type of solution we are creating. With that said, your statement "responsability is primarily internal" is not right if you are taking about the term in the framework of RACI or similiar (the "R" in the model). The way of acting is totally independent of the location of the role. Why? Because is a matter of strategical decision if you assign a way of acting to an external or internal role. One thing that can be help a lot to define a RACI or similar is the CRUD matrix. CRUD matrix is not in the scope of the project manager but is in the scope of business analyst and because business analyst is in charge of solution definition and because the solution definition is the source for creating or related to project then it is critical to take into account.
avatar
Abolfazl Yousefi Darestani Manager, Quality and Continuous Improvement| Hörmann-TNR Industrial Doors Newmarket, Ontario, Canada
Sergio made good points.
avatar
Mohd Azmirul Adha Azmir Project Manager| Buildserve Engineering Puchong, Selangor, Malaysia
Don't get me wrong.. I prefer do it my way and blend with new knowledge and education n see the results. If u can see I do get retrenchment almost 4 months now.. A few controversial statements I did get from my so call colleagues who are proud of it and the ones who take the credits from my project management and I get kick after doing T&C. If I not do it that way, I don't get the reals one and why nobody notices about it in my organisation.
avatar
Mohd Azmirul Adha Azmir Project Manager| Buildserve Engineering Puchong, Selangor, Malaysia
I do update in my LinkedIn from start till end of project.
avatar
Keith Novak Tukwila, Wa, United States
There appear to be multiple levels of responsibility in this question.

For broad assignment of responsibilities, a RACI or similar type matrix may be used. At the task level, this information is included in what PMI refers to as the WBS Dictionary (also known by other names outside PMI).

Please login or join to reply