We are running a project which is calculated from the Finish Date. I have a task that should complete 60 days prior to the project finish date of the final task. I figured ###FS-60 days, where ### is the final task number, would do the trick, but the end date of the predecessor task shows as the project end date. It stays that date no matter what relationship I assign to the dependency.
Questions: 1) Is it the "Calculate From Project Finish" that is causing the issue; and 2) What change do I make to have the end date of the predecessor task at 60 days prior to final? Thanks! Saving Changes...