Pandemic effect on construction projects

linkedin twitter facebook  
avatar
YAAZH THILIBAN SETHURAMAN Construction manager| Raffa construcion and maintenance co.W.L.L Manama, Bahrain
will this pandemic effect on cost and schedule impacts in construction projects can be taken as a force majeure? any way of claims for this?
comments are most welcome
Sort By:
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Yaazh -

this question was asked a number of times in different threads since March 2020. Here are a couple of these:

1. https://www.projectmanagement.com/discussi...orce-Majeure---
2. https://www.projectmanagement.com/discussi...-Force-Majeure-

Kiron
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
You have to go back to your contract term and conditions. In theory, yes, this could be considered as force majeure as it’s a force of nature.