question of RMP exam as :

linkedin twitter facebook  
avatar
Mazin AL-Rubaye Projects Manager| Towers Technology Construction Company Abu Dhabi, Abu Dhabi, United Arab Emirates
Q: Which of the following is an input to schedule metrics?
A- WBS
B- RBS
C- Critical path method
D- OBS
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Mazin -

This is a horrible question. Inputs are to processes and there is no process in the PMBOK called "Schedule Metrics". If we are referring to metrics used to gauge our schedule performance, I don't believe any of the answer choices are valid.

Kiron