Project Calendar...

linkedin twitter facebook  
avatar
Lilian Seow Intracorp Projects Ltd. British Columbia, Canada
PMBOK, page 220, 6.5.3.4;
"A schedule model may require more than one project calendar to allow for different work periods for some activities to calculate the project schedule."

How is it possible to have "more than one project calendar" in the same one schedule model [assuming Microsoft Project software] ?

Thank you.
Sort By:
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Lilian -

I believe they are using the term "project calendar" in a different manner than how it is used with MSP. In MSP, a schedule can have only one effective project calendar. What I believe is meant in the PMBOK Guide is what we'd call a task calendar in MSP.

Kiron
...
1 reply by Lilian Seow
Feb 14, 2021 6:19 PM
Lilian Seow
...
Thank you Kiron. That task calendar makes sense to have more than one.
avatar
Lilian Seow Intracorp Projects Ltd. British Columbia, Canada
Feb 14, 2021 6:14 PM
Replying to Kiron Bondale
...
Lilian -

I believe they are using the term "project calendar" in a different manner than how it is used with MSP. In MSP, a schedule can have only one effective project calendar. What I believe is meant in the PMBOK Guide is what we'd call a task calendar in MSP.

Kiron
Thank you Kiron. That task calendar makes sense to have more than one.
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
You have to have multiple project calendars and multiple resource calendars to create one schedule just in case it applies. Inside Microsoft Project you have the possibility to create them and assign them at project and resource levels. Just to comment something obvious if you go to Microsoft Project web page and make a search you will find about it.
...
1 reply by Lilian Seow
Feb 15, 2021 3:45 PM
Lilian Seow
...
Thank you Sergio. Yes, you are right. I can apply different calendar settings for the different resources in the same Microsoft Project Schedule.
avatar
Lilian Seow Intracorp Projects Ltd. British Columbia, Canada
Feb 15, 2021 7:25 AM
Replying to Sergio Luis Conte
...
You have to have multiple project calendars and multiple resource calendars to create one schedule just in case it applies. Inside Microsoft Project you have the possibility to create them and assign them at project and resource levels. Just to comment something obvious if you go to Microsoft Project web page and make a search you will find about it.
Thank you Sergio. Yes, you are right. I can apply different calendar settings for the different resources in the same Microsoft Project Schedule.