Mar 14, 2021 9:28 AM
Replying to Kiron Bondale
...
Abubakar -
The schedule baseline represents a snapshot of (usually) an approved project schedule. It is used as the basis for performance assessment and reporting. Over the life of the project, the start and end dates of individual activities might change, but the baseline should not be updated until a formal change is accepted at which time a new baseline snapshot can be taken.
The critical path represents the longest sequential path of activities from the start of your project to the end, which also defines the shortest duration in which the project could be completed.
To understand the relationship between the two, the schedule end date from your baseline is defined by the critical path.
Kiron