Inputs for 7.2 Estimate Cost

linkedin twitter facebook  
avatar
Lilian Seow Intracorp Projects Ltd. British Columbia, Canada
Why is Resource Management Plan not an input for Estimate Cost but an input for Develop Budget?

7.3.1.1. clearly states resource management plan provides information for rates, esstimation of travel costs, and other foreseen costs are necessary to estimate the overall project budget. So, why this is not relevant for Estimate Cost process?
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Resource management plan is a component inside the Project Plan and the Project Plan is an input of Estimate Cost. But if we talk about what is explicit stated then Resource Requirements contains all the information needed to estimate costs. For Develop Budget you need the line of time then Resource Management Plan is needed to do that. Just to comment, where I was part of the group which wrote the PMBOK, discussions about the level of detail in this type of things was debated. In my opinion it do not add value.