Shimonkepha Onwuneme Senior Planner| NKT AB Awka, Anambra, Nigeria
Two ways to determine how risky a project is at a glance (even before Risk Identification and Analysis) using the Schedule and Network Diagram

1. The number of critical paths: the higher the number, the riskier a project is


2. Path Convergence: the points at which multiple activities converge into or out of a single activity shows risk. That is activities with either or both multiple predecessors or successors.

The higher the multiplicity of convergence and the overall number of occurrences of convergences, the riskier the project.



Do you know any other method?
Sort By:
< 1 2 >
Certainly Shimonkepha, my observation was a complementary method mainly used at the conceptualization stage of a project because there are many ways to identify them.
avatar
Amr Abd El Azim United Arab Emirates
First look to the Project Contract can give you hint :
1- Payment Terms
2- LD Clause
3-Deliverables Milestone Dates
4-General Technical Specifications
< 1 2 >

Please login or join to reply

Content ID:
ADVERTISEMENTS

"It isn't necessary to be rich and famous to be happy. It's only necessary to be rich."

- Alan Alda

ADVERTISEMENT

Sponsors