Back to back payment for the main contractor and its subcontractors?
Arnel FranciscoSenior Estimator/Cost ControlPasig City, Philippines
I wanted to know up to extent from the agreed scope of work, payments on variations? and how does it affects the privity of the contracts between the main contractor and client? Saving Changes...
Sort By:
Thomas WalentaGlobal Project Economy ExpertHackenheim, Germany
Arnel,
since the buyer and then main contractor should do some integration and quality assurance work on the subcontractor deliverables, back to back is a bad idea. And the risk of gaps lies fully with the buyer and main contractor.
Privity can be limited by contractual language, e.g. subcontractor selection needs buyer approval, ability to conduct onsite visits and audits, or subcontractor required to report in a standard format. Be aware though, if you limit privity you will probable have to pay a premium. Avoid micromanagement, so select a main contractor you can trust.
Thomas
...
1 reply by Arnel Francisco
Nov 02, 2021 4:43 AM
Arnel Francisco
...
Hi Thomas,
Thank you for your reply.
Saving Changes...
Peter RapinSubject Matter Expect; Project Delivery| Independent ConsultantOntario, Canada
The main issue with back-to-back payment (paid-when-paid) between prime contractor and subcontractor is that it benefits the prime only The sub may be waiting for payment due to disagreements between the prime and owner that has nothing to do with the sub's performance. The prime could use the clause to "bully" the sub into performing work not specified in the contract or just stretch out payments for financial advantage. "I forgot to include for your work in the billing cycle thus you won't get paid." The sub may have no way of validating the prime's claim of non-payment. In some jurisdictions is is illegal to have 'paid-when-paid' contract clauses to protect subs from aggressive primes.
As to contract privity, it depends entirely on the contract terms. The contract between the owner and prime may have confidentiality clauses limiting the sub's access. The sub only has access to the terms of the owner-prime contract if it is so stated in the prime-sub contract and allowed under the owner-prime contract.
Bottom line: paid-when-paid contracts are at significantly higher risk of delayed payment for the sub. If you are going to enter into such a contract make sure you consider the risks and apply mitigation measures including how you can finance the delay and/or influence the owner-prime payment process.
we have been in a main contractor and a subcontractor position, and have been on the "giving" end of the "grieve" (where we are main) and the receiving end (where we are sub).
All is dependent on the relationships you have, do you want to work for that main again or not, etc. Typically, as a sub, and we are forced into paid-when-paid contract, we would always add a clause that limits the delay:...."but payment not later than..." we would never enter into an open-ended contract without that clause. The contract language should always be such that (as a sub) the prime would not be able to stop you to put a lien on the deliverable, even if that deliverable is already at the Buyer's. (the fly in the ointment of course is that the Buyer is not party to the Prime / sub contract). All of our business is international, and putting a lien on a deliverable therefore is usually very expensive. So our contracts specifically would have at least one paragraph on transfer of title. If as a sub, we already have a good relationship with the buyer, we would normally try to advise the buyer at the time of Prime / sub contract)
...
1 reply by Arnel Francisco
Nov 02, 2021 4:47 AM
Arnel Francisco
...
Hi Roland,
Thanks.
Saving Changes...
Arnel FranciscoSenior Estimator/Cost ControlPasig City, Philippines
Oct 31, 2021 9:16 AM
Replying to Thomas Walenta
...
Arnel,
since the buyer and then main contractor should do some integration and quality assurance work on the subcontractor deliverables, back to back is a bad idea. And the risk of gaps lies fully with the buyer and main contractor.
Privity can be limited by contractual language, e.g. subcontractor selection needs buyer approval, ability to conduct onsite visits and audits, or subcontractor required to report in a standard format. Be aware though, if you limit privity you will probable have to pay a premium. Avoid micromanagement, so select a main contractor you can trust.
Thomas
Hi Thomas,
Thank you for your reply. Saving Changes...
Arnel FranciscoSenior Estimator/Cost ControlPasig City, Philippines
Oct 31, 2021 10:52 AM
Replying to Peter Rapin
...
The main issue with back-to-back payment (paid-when-paid) between prime contractor and subcontractor is that it benefits the prime only The sub may be waiting for payment due to disagreements between the prime and owner that has nothing to do with the sub's performance. The prime could use the clause to "bully" the sub into performing work not specified in the contract or just stretch out payments for financial advantage. "I forgot to include for your work in the billing cycle thus you won't get paid." The sub may have no way of validating the prime's claim of non-payment. In some jurisdictions is is illegal to have 'paid-when-paid' contract clauses to protect subs from aggressive primes.
As to contract privity, it depends entirely on the contract terms. The contract between the owner and prime may have confidentiality clauses limiting the sub's access. The sub only has access to the terms of the owner-prime contract if it is so stated in the prime-sub contract and allowed under the owner-prime contract.
Bottom line: paid-when-paid contracts are at significantly higher risk of delayed payment for the sub. If you are going to enter into such a contract make sure you consider the risks and apply mitigation measures including how you can finance the delay and/or influence the owner-prime payment process.
Hi Peter,
Thanks. Saving Changes...
Arnel FranciscoSenior Estimator/Cost ControlPasig City, Philippines
Oct 31, 2021 4:47 PM
Replying to Roland Vander Straeten
...
we have been in a main contractor and a subcontractor position, and have been on the "giving" end of the "grieve" (where we are main) and the receiving end (where we are sub).
All is dependent on the relationships you have, do you want to work for that main again or not, etc. Typically, as a sub, and we are forced into paid-when-paid contract, we would always add a clause that limits the delay:...."but payment not later than..." we would never enter into an open-ended contract without that clause. The contract language should always be such that (as a sub) the prime would not be able to stop you to put a lien on the deliverable, even if that deliverable is already at the Buyer's. (the fly in the ointment of course is that the Buyer is not party to the Prime / sub contract). All of our business is international, and putting a lien on a deliverable therefore is usually very expensive. So our contracts specifically would have at least one paragraph on transfer of title. If as a sub, we already have a good relationship with the buyer, we would normally try to advise the buyer at the time of Prime / sub contract)
Caro Arnel,
When you work with sub-contractors is essential to understand that your main contract must be a mirror for the sub-contractor. Otherwise, you would take some risk. So you should at least include such potential impact in your contingency.
The only way to assure that your sub-contractor is aligned with your client is by making the sub-contractor complies with the same commercial conditions and clauses.
However, always depending on what was agreed in the contract with your sub-contractor, the relationship between the client and the main contractor is individual, your sub-contractor has not entitled to participate, especially in terms of payment.
...
2 replies by Arnel Francisco and Peter Rapin
Nov 03, 2021 2:31 AM
Arnel Francisco
...
Hi Elena,
Thanks.
Nov 03, 2021 9:47 AM
Peter Rapin
...
The purpose of a contract is to document the sharing of risk. As a prime the owner assigns you risk and compensates accordingly. If, as the prime, you choose in turn to assign the risk to a sub then you have to compensate accordingly. The only risk you can fairly assign to the sub is the risk directly associated with the work included in the assignment. For example, you cannot assign total project delivery risk to the sub if the sub is only contracted to do the brick work.
However, you can reasonable assign planning, monitoring and reporting obligations such as weekly updates etc. but you have to compensate for that service. Most primes prefer to allow the subs to deliver their specific trade (lay bricks) and not have to pay the premium for the administrative stuff.
Bottom line: only include in the contract for what you you are prepared to pay for.
Saving Changes...
Arnel FranciscoSenior Estimator/Cost ControlPasig City, Philippines
Nov 02, 2021 9:24 AM
Replying to Elena Sandoval
...
Caro Arnel,
When you work with sub-contractors is essential to understand that your main contract must be a mirror for the sub-contractor. Otherwise, you would take some risk. So you should at least include such potential impact in your contingency.
The only way to assure that your sub-contractor is aligned with your client is by making the sub-contractor complies with the same commercial conditions and clauses.
However, always depending on what was agreed in the contract with your sub-contractor, the relationship between the client and the main contractor is individual, your sub-contractor has not entitled to participate, especially in terms of payment.
Hi Elena,
Thanks. Saving Changes...
Peter RapinSubject Matter Expect; Project Delivery| Independent ConsultantOntario, Canada
Nov 02, 2021 9:24 AM
Replying to Elena Sandoval
...
Caro Arnel,
When you work with sub-contractors is essential to understand that your main contract must be a mirror for the sub-contractor. Otherwise, you would take some risk. So you should at least include such potential impact in your contingency.
The only way to assure that your sub-contractor is aligned with your client is by making the sub-contractor complies with the same commercial conditions and clauses.
However, always depending on what was agreed in the contract with your sub-contractor, the relationship between the client and the main contractor is individual, your sub-contractor has not entitled to participate, especially in terms of payment.
The purpose of a contract is to document the sharing of risk. As a prime the owner assigns you risk and compensates accordingly. If, as the prime, you choose in turn to assign the risk to a sub then you have to compensate accordingly. The only risk you can fairly assign to the sub is the risk directly associated with the work included in the assignment. For example, you cannot assign total project delivery risk to the sub if the sub is only contracted to do the brick work.
However, you can reasonable assign planning, monitoring and reporting obligations such as weekly updates etc. but you have to compensate for that service. Most primes prefer to allow the subs to deliver their specific trade (lay bricks) and not have to pay the premium for the administrative stuff.
Bottom line: only include in the contract for what you you are prepared to pay for. Saving Changes...
Arnel FranciscoSenior Estimator/Cost ControlPasig City, Philippines