Resource report plan based on a resource pool using a Assignment usage visual report in MS Project 2010. When I try to select the level of usage data to include in the report I can only do years or

linkedin twitter facebook  
avatar
Anonymous
Hi I hope you can help. I am making a resource report plan based on a resource pool using a Assignment usage visual report in MS Project 2010. When I try to select the level of usage data to include in the report I can only do years or quarters. If I attempt to go to months (which is the option I need) I get an error message: "Your project is too large to support reporting at the level of data you have chosen" Does anyone know if this is due to too many projects using the resource pool or too many features in the report template? Thanks for your help in advance. I am using MS Project 2016 Professional.
Sort By:
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
I found a similar issue reported here a few years back: https://social.technet.microsoft.com/Forum...onal2010general

Kiron
avatar
Stéphane Parent Self Employed / Semi-retired| Leader Maker Prince Edward Island, Canada
If the problem is similar to the one highlighted by Kiron, it should be fixed in Project 2016 Professional.