Resource report plan based on a resource pool using a Assignment usage visual report in MS Project 2010. When I try to select the level of usage data to include in the report I can only do years or
Anonymous
Hi I hope you can help. I am making a resource report plan based on a resource pool using a Assignment usage visual report in MS Project 2010. When I try to select the level of usage data to include in the report I can only do years or quarters. If I attempt to go to months (which is the option I need) I get an error message: "Your project is too large to support reporting at the level of data you have chosen" Does anyone know if this is due to too many projects using the resource pool or too many features in the report template? Thanks for your help in advance. I am using MS Project 2016 Professional. Saving Changes...