Project Management

Please login or join to subscribe to this thread

Microsoft Project and Time Over-run

linkedin twitter facebook  
avatar
Hafeez Rahman Teacher| Bahria University Karachi, Pakistan
I am trying my hand on MS Project 98. I find it fascinating except for a problem in Time Over-run. It calculates time over-runs by deducting BCWP from BCWS.

At 100% completion, the BCWP would always be equal to BCWS and the difference would be zero. In other words, the time overruns would be NONE. Supposing a project was completed in 4 weeks as against its scheduled completion of 3 weeks, this indicates a delay of one week. If the same data were fed to MS Project, the SV would be ZERO.

In Excel, I can work out the time over-run by deducting BCWP in days from Actual Days. Obviously, BCWP in term of days, at 100% completion, would be 18 days (3 weeks x 6 days/week), while four weeks or 24 days have gone by, showing a time over-run of 6 days.

How can I do this in MS Project?

Shall be grateful for an early advice.
avatar
Simon Sinnott Melbourne, Vic, Australia
Have you saved your baseline?

MSP would most likely make BCWP and BCWS equal if you have not set the baseline.

Please login or join to reply

Content ID:
ADVERTISEMENTS

"Humanity has advanced, when it has advanced, not because it has been sober, responsible and cautious, but because it has been playful, rebellious and immature."

- Tom Robbins

ADVERTISEMENT

Sponsors