MS Projects - KPI metrics

linkedin twitter facebook  
avatar
Denathayalan Ramasamy Chief Technology Officer| Atal Incubation Centre -CIIC Chennai, Tamilnadu, India
Have you configured Earned Value Management metrics in MS projects?

So far I have used it only for WBS, defining & sequencing activities, % of completion of status. Please suggest if you have any other advanced features
Sort By:
avatar
Justin Fu Senior Systems Engineer| Parsons Bristow, Va, United States
Thanks, would like to hear more
avatar
Vijay Suryavanshi Project Manager - Engineering| RECARO Aircraft Seating Plantation, Fl, United States
You can't in MS Project. Though it automatically spits out some EVM reports.

Main thing you would look for is Cost variance and schedule variance. And this can be developed in a n excel sheet. Comparing your planned value (cost/schedule) to actual values. (cost/schedule).

Hope this helps.