Jul 31, 2024 2:22 PM
Replying to M. Hosney Abdelgelil
...
Greetings y'all. I am in a serious debate with a contractor that his baseline schedule should match exactly the time stipulated in the contract. The contractor said he can finish the project in less time than the contract and I advised him to comply with the contract for the Baseline and then logically provide for an earlier date if he wishes.
I am reluctant to approve a baseline that is shorter than the contract duration in worries over future disputes. Any one had a similar situation and maybe wrote a disclaimer for the approval under this premis?
Thanks in advance.