Dec 06, 2022 7:46 AM
Replying to Kiron Bondale
...
Luis -
Integrating a deliverable is different than what the PMBOK Framework would term "Integration Management". The latter relates to the orchestration work of the PM - the glue binding all the other knowledge areas together. Your question is more specific about building the product/service/result requested by the stakeholders.
Depending on the context of the project scope, integration might happen continuously (e.g. a software application is constantly being built and tested as code changes are happening) or on a regular basis (e.g. at the end of an iteration or at regular scheduled intervals).
The former is ideal as it enables as short a product/service/result feedback loop as one could hope for. The latter can increase the risk of building the wrong product or building the product wrong.
Kiron