Definition of EV is EV

linkedin twitter facebook  
avatar
Gerald Friesen Senior Project/Operations Manager| mCloud Technologies Inc. St. Albert, Alberta, Canada
Table 1-2. Earned Value Calculations Summary Table Equation for EV is EV = sum of the planned value of completed work.
Do I interpret this by the Lexicon definition of PV?
If so, EV = sum of the authorized budget value of completed work.
Sort By:
avatar
Keith Novak Tukwila, Wa, United States
Correct. Planned value is the budgeted cost we assigned to each task due to be completed at any point in time. Earned value is the budgeted cost of the tasks actually completed at that point.

If you planned to have 2 task complete and each is 10 hours, your PV is 20. If you only completed one of those tasks, your EV is 10. This is not to be confused with Actual Cost (AC) which is what it took to complete the planned tasks. If you completed both tasks, but each took 12 hours, your EV is 20, your AC is 24, compared to your PV of 20.
...
1 reply by Gerald Friesen
Jan 19, 2023 1:55 PM
Gerald Friesen
...
Thanks for the confirmation. We are implementing a new PM module and the vendor has misinterpreted the calculation linking the PV to the schedule which causes the EV to fluctuate based on time not actual work completed. As the schedule advances, the EV changes without any progress in completing tasks.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Gerald

Earned Value (EV) is the same as Budgeted Cost of Work Performed (BCWP)

RK
avatar
Abolfazl Yousefi Darestani Manager, Quality and Continuous Improvement| Hörmann-TNR Industrial Doors Newmarket, Ontario, Canada
Yes, correct.
avatar
Vijay Suryavanshi Project Manager - Engineering| RECARO Aircraft Seating Plantation, Fl, United States
Keith explains it very well ! Agreed.
avatar
VerĂ³nica Elizabeth Pozo Ruiz RYLAI Access Control Quito, Pichincha, Ecuador
Since PV and EV are different considerations, as Keith explained, we can determine that if the earned value is greater than the planned value, this indicates that the project is ahead of schedule; and contrary, if the earned value is lower than the planned value, this indicates that the project is behind of schedule.
avatar
Gerald Friesen Senior Project/Operations Manager| mCloud Technologies Inc. St. Albert, Alberta, Canada
Jan 12, 2023 7:25 PM
Replying to Keith Novak
...
Correct. Planned value is the budgeted cost we assigned to each task due to be completed at any point in time. Earned value is the budgeted cost of the tasks actually completed at that point.

If you planned to have 2 task complete and each is 10 hours, your PV is 20. If you only completed one of those tasks, your EV is 10. This is not to be confused with Actual Cost (AC) which is what it took to complete the planned tasks. If you completed both tasks, but each took 12 hours, your EV is 20, your AC is 24, compared to your PV of 20.
Thanks for the confirmation. We are implementing a new PM module and the vendor has misinterpreted the calculation linking the PV to the schedule which causes the EV to fluctuate based on time not actual work completed. As the schedule advances, the EV changes without any progress in completing tasks.
avatar
Latha Thamma reddi Sr Product and Portfolio Management (Automation Innovation)| DXC Technology Mckinney, Tx, United States
Thanks for sharing.