I want to create a dashboard chart showing the typical PV, EV, and AC. However I'd like to show the entirety of PV, including PV for future dates all the way to the Go Live milestone. Any idea how to get future PV by period out of MS Project?
Thanks,
Erik Saving Changes...
Gary HarveyVP Technical Services| PinnacleVienna, Va, United States
Erik - go to the Resource Usage view. You can right click in the spreadsheet area to adjust the values being shown. Saving Changes...