Mary Grace LazoProject Manager| SMITS, Inc.Mandaluyong, Philippines
Hello, I am attending a review session for PMP Certification, though I am not yet going to take it.
We had a practice exam yesterday and we encountered a little confusing question. Just want to get your input regarding this. Here was the question:
The project life cycle differs from the product life cycle in that the project life cycle:
A. Does not incorporate a methodology
B. Is different for each industry
C. Can spawn many projects
D. Describes project management activities
My answer was B, and it was correct based on the answer sheet but we had conflicts with the other on the group because they said the item also applies for Product life cycle, thus it should not be the correct answer. The answer should be D.
Just wanted to know what will be your answer here and why.
Hi Mary Grace, there are so many tricky questions on PMP exam, specially for the updated one. I suggest you take the mock exams from PMChamp which are versions of the new exam
If you are aiming to take PMP practice test exam then give a try to Testmayor exam dumps. We are offering valid PMP PDF exam dumps with real exam questions verified by our professional experts. You can check the validity of PMP exam dumps by trying the free demo available at Testmayor. https://www.testmayor.com/PMP-test.html Saving Changes...