snake diagram in MS Project

linkedin twitter facebook  
avatar
Torge Oeverdiek Danfoss Editron Sh, Germany
Hi team , I want to create a snake diagram for my project schedule. This is a diagram showing Cumulative duration on the Y axis and Critical Path Milestone Number on the X axis. It plots the Actual Time to completion for each milestone vs Schedules Time to Completion for the same . It's an excellent way to visualize schedule health (deviation of Actual vs. baseline completion dates for milestones) but for some reason I cannot find a way to create such a view in MS Project. Can somebody help? Prob I am missing something obvious here :D