Construction Scheduling in Coal mining environment

linkedin twitter facebook   Construction  
avatar
Belizário Alberto Construction Project Manager, PMI-SCP, PMP, PMI-CP, FIDIC Practitioner | Absa Bank Mozambique Maputo, Mozambique
Coal mines are so dynamic that is quite complicated to adhere to schedule baselines. How can we implement an effective plan in the mining environment to reduce schedule change rate?
Sort By:
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Belizário -

I'd suggest a rolling wave approach might be appropriate with schedule commitments made at the near term milestone level only with future milestone commitments made based on regular re-planning resulting from new information.

Kiron
avatar
Abolfazl Yousefi Darestani Manager, Quality and Continuous Improvement| Hörmann-TNR Industrial Doors Newmarket, Ontario, Canada
Kiron's suggestion makes sense.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
You need to take an adaptive approach in planning and as suggested by Kiron, Rolling Wave planning could be a suitable approach in this case.