How to prepare recovery schedule using primavera when the predictive projects baseline schedule has slipped and CCB has approved to change the baseline specially in predictive projects like major oil

linkedin twitter facebook   Agile   Change Management   Scope Management  
avatar
Sharique Aman West Champaran, Br, India
How to prepare recovery schedule using primavera when the predictive projects baseline schedule has slipped and CCB has approved to change the baseline specially in predictive projects like major oil and gas construction..
Sort By:
avatar
Kimberly Whitby
PMI Team Member
Online Community Specialist| PMI Newtown Square, Pa, United States
Hello Sharique - and welcome to PMI's Online Community! Congratulations on taking your first step in joining our community. In regard to your inquiry, I encourage you to search our wide variety of content located within the 'Templates' drop-down at the top of our page and/or our Discussion threads. Here you can find some tools/previous answers to assist you. One particular discussion thread you may find helpful is https://www.projectmanagement.com/discussi...ng-is-required. Perhaps adding your question to this particular thread will generate responses from those who previously replied. You can then network and explore even more tools and techniques.

I hope this helps, and as a new community member, please take a moment to introduce yourself to PMI’s Online Community at https://www.projectmanagement.com/discussi...line-community.
avatar
Keith Novak Tukwila, Wa, United States
Sharique,

I am not an expert using Primavera, but have worked side-by-side with expert users to fix these kinds of problems. It is an excellent tool for this.

Change the dates of the things that caused your schedule slide to your current best estimate and generate your critical path. That will cause a lot of errors. Fortunately it is an excellent program for debugging schedule errors.

Then you can evaluate the errors and the constraints violated. If a flow is too long, can it be compressed? If two tasks are ideally performed finish-to-start, can they be overlapping? Where are your opportunities?

Theory of Constraints proves itself over and over in practice that you want to look for the biggest constraint in your schedule and focus on that opportunity first.

Good luck!
Keith