When closing a project or phase, part of the process may require the use of which type of analysis?

linkedin twitter facebook   Career Development  
avatar
Anonymous
So I was trying to look up the final right answer and unforunately ExamTopics didn't have this question posted. I'm now confused whether the answer would be B. Regression Analysis or C. Document Analysis. 

A . Reserve analysis
B . Regression analysis
C . Document analysis
D . Product analysis
 
Sort By:
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Personally, I would chose C because the rest are done either at the outset of the project, or throughout. I am not sure why would you do regression analysis as part of the closure process. Document analysis makes more sense to me!
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
This is an odd question. I wouldn't see Regression or Product Analysis being valid for the end of a phase or project as those are likely done mid-phase or early phase.
Reserve analysis is feasible, especially at the end of a phase to know how much you have left relative to what you expect to need for future phases. Document analysis is a generic term. As such, I'd go with A as it is more specific but C likely covers almost anything you'd do at that point :-) !

Kiron
avatar
VerĂ³nica Elizabeth Pozo Ruiz RYLAI Access Control Quito, Pichincha, Ecuador
C. Document Analysis would be the best option. The other mention processes that are done in other phases of the project.
avatar
Nicole Petite ATP/Project Manager/Scrum Master| ProjIT Solutions Al, United States
Definitely C.

Please login or join to reply