The deliverable does not meet the agreed upon quality standards. The problem is from a external vendor supplied part. They are unwilling to correct the problem. What should the PM do. 

1) Check the SLA with the vendor
2) Review the procurement management plan and contract agreements

#2 is the correct answer according to PMP's practice exam. Why wouldn't checking the SLA (that's a contract) be a more appropriate response since it is specific to the supplier? 
Sort By:
< 1 2 >
avatar
Jon ONeil Tubelite USA Mi, United States
Thank you Sir! This helped immensely. It confirmed that my mindset is in the correct place and gives me confidence that your answers are in line with what I would of chosen. The practice exam does tell you if you are right or wrong, but lacks explanation (in this case). I will defiantly look at the PM PrepCast, thank you for the recommendation.

Thank you for taking the time to explain this in detail. This is invaluable to me. Also, thank you for being such a huge contributor for new people like myself.
...
1 reply by Rami Kaibni
Mar 02, 2024 1:54 AM
Rami Kaibni
...
You’re very welcome, Jon. Glad I was able to help. Good luck with your exam!
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Mar 01, 2024 6:07 PM
Replying to Jon ONeil
...
Thank you Sir! This helped immensely. It confirmed that my mindset is in the correct place and gives me confidence that your answers are in line with what I would of chosen. The practice exam does tell you if you are right or wrong, but lacks explanation (in this case). I will defiantly look at the PM PrepCast, thank you for the recommendation.

Thank you for taking the time to explain this in detail. This is invaluable to me. Also, thank you for being such a huge contributor for new people like myself.
You’re very welcome, Jon. Glad I was able to help. Good luck with your exam!
avatar
Jon ONeil Tubelite USA Mi, United States
I have another scenario that I need help understanding. Below is the situation....

A project manager has the following for a new project....
1) Assumptions
2) Restrictions
3) Preliminary Scope

The answer options are as follows....
1) Review and understand the business case and project goals
2) Put together a project team
3) Build a project schedule
4) Ensure project charter approval is obtained from sponsor

Maybe I am wrong, but # 2 & #3 are obviously wrong. The project charter is an INPUT of the preliminary scope. Don't you need the business case and project goals in order to develop the charter?
< 1 2 >

Please login or join to reply

Content ID:
ADVERTISEMENTS

A celebrity is a person who works hard all his life to become known, then wears dark glasses to avoid being recognized.

- Fred Allen

ADVERTISEMENT

Sponsors