Le (Maria) CaiMaster Student| Northeastern UniversitySunnyvale, CA, United States
When I was taking a risk management course at school, our professor had an exercise with us. The main goal was to distinguish between negative risks (threats) and positive risks (opportunities), which I found rather confusing. For example, community objection in a project - it can be negative, as it will postpone the delivery of your project if they don't agree with it; it can also be positive, as it can give you alternative perspectives on potential improvements.
So, my questions are (feel free to share your thoughts on any of them):
1. As the title says, Do we have to categorize risks as negative or positive? 2. Is it possible that risks can be both negative and positive? 3. Is my example a good way to understand it? 4. If my example isn't a good example, but you agree with point 2, would you provide another proper example? Saving Changes...
Le (Maria) CaiMaster Student| Northeastern UniversitySunnyvale, CA, United States
Jun 11, 2024 6:33 PM
Replying to Sergio Luis Conte
...
After 40 years working on this matter I never was in a place where risk were categorized as negative or positive. No matter that, when I was professor in courses I teach that. In the real life I always used risk and issue clasiffication adding to that a probability of occurrence and an action to convert risk in opportunities no matter they help to avoid or mitigate them
Haha, thank you for sharing your experience! It’s both reassuring and interesting to learn! Saving Changes...
Le (Maria) CaiMaster Student| Northeastern UniversitySunnyvale, CA, United States
Jun 11, 2024 11:13 PM
Replying to Khai Ng.
...
Maria,
1. As the title says, Do we have to categorize risks as negative or positive?
--> Yes, beause each type of risk need a different plan to treat.
2. Is it possible that risks can be both negative and positive?
--> Each coin has two sides so the answer is Yes, but think about the main effect when you categorize risks.
3. Is my example a good way to understand it?
--> Yes, it is. But the main effect of Community Objection is the delay of the project, so it should be categorized as Negative. Even we know that it may provide an oppotunity to explore different perspectives, it is still a secondary effect. So in this case we may have a Secondary Risk, that is the result of the first risk (Community Objection), the Secondary Risk may be categorized as Positive, it will result in obtaining different perspectives that can be exploited to improve solution. Think about the major effect as uncertaint events or conditions occur when categorizing your risks.
Dear Khai,
Thank you for your valuable input. I appreciate your approach of categorizing effects as "main effects" and "secondary effects." It’s a very clear and intuitive way to understand the potential outcomes of risks.
Also, thank you for using this model to explain my example. It’s now much clearer to me.
Maria
Saving Changes...
Le (Maria) CaiMaster Student| Northeastern UniversitySunnyvale, CA, United States
Jun 12, 2024 9:39 AM
Replying to Eduard Hernandez
...
It comes down to semantics. When people hear the term "risk," they often think of potential loss, devaluation, or failure. The phrase "take the risk" can lead to either a positive or negative outcome. In the former case, the risk (threat) turns into an opportunity. However, calling this a "positive risk" might be a bit of a stretch.
*Positive risk* does sound awkward to me as well. I guess that’s why I was confused in class at first! Saving Changes...
Le (Maria) CaiMaster Student| Northeastern UniversitySunnyvale, CA, United States
Jun 14, 2024 12:47 PM
Replying to Francisco Herrera
...
Le María,
I prefer to think of negative risks as threats and positive risks as opportunities.
For threats, I consider anything that puts the project's objectives at risk, and for opportunities, I consider anything that supports exceeding the objectives.
I hope this helps, greetings!
Thank you for your input, Francisco! I appreciate your perspective of thinking about negative risks as threats and positive risks as opportunities. It’s a helpful way to visualize them.
Maria Saving Changes...
Le (Maria) CaiMaster Student| Northeastern UniversitySunnyvale, CA, United States
I want to thank everyone who has joined the conversation. Your insights have been invaluable, and I’ve learned a great deal from all of you (and likely those who are reading this discussion as well).
Here’s my summary of the key takeaways from our conversation on risk evaluation:
Cumulative Impact: The overall impact of a risk, considering both positive and negative consequences, is crucial for evaluation.
Categorization: While risks can be categorized as positive or negative, it’s important to consider the primary effect and potential secondary effects.
Quantitative Methods: Quantitative methods can be used to make risk analysis more visual and straightforward.
The term “positive risk” can be somewhat awkward. In a professional setting, “opportunity” might be a more commonly used term.
Insightful comments so far. I also learnt a lot Saving Changes...
Sachin AggarwalCountry Sales Manager (IOT, Japan)| BlackBerry Tokyo, Japan
Hello Maria This is an interesting question. Please let me share my views on this. Starting with the basics. 1. Risk refer to the uncertainty in an outcome. For example, it normally takes 7 days (expected outcome) for a shipment to arrive from Japan to UK, but we have seen a variation of plus/minus 1 day in this schedule in the past. This variation is the risk associated with this delivery. I am not going into statistics to keep things simple.
2. Plus 1 day in delivery is a “negative risk”, and Minus 1 day in delivery will be a “positive risk”. So, as per my understanding, we should have two records for this risk in our plan: One as positive and one as negative. As this risk is a minor one, probably the strategy would be to “accept” for both cases. Just monitor with no special action needed.
Now, coming to your specific questions.
1, As the title says, Do we have to categorize risks as negative or positive? Yes, any risk has to be categorized either as positive or negative. Risk is the uncertainty and it will go one way or the other.
2. Is it possible that risks can be both negative and positive? Yes, I have given an example above.
3. Is my example a good way to understand it? Not sure about this. Let’s say you plan to complete the project is 100 days. Due to community objections, the project can potentially delay by 10 days. Then, we have a negative risk here. Now, you engage the community stakeholder, and as a part of risk response, you decide to change the project objectives while extending the schedule of the project to 110 days. I will not call it a positive risk. The negative risk materialized and as a result your project baseline schedule is delayed by 10 days. Project team “accepted” the risk.
4. If my example isn't a good example, but you agree with point 2, would you provide another proper example? I have already given an example above.
I hope this helps. Thank you for sharing this interesting question. Regards Sachin
In risk management, the process where we need to classify risks into positive or negative is when Planning Risk responses:
* There is a set of strategies for negative risks, that include avoiding, transferring, mitigating, or accepting the risk.
* For the other part, the strategies for positive risk or opportunities are: exploiting, enhancing, sharing, or accepting the risk. Saving Changes...
Eric SimmsSenior Program ManagerBaltimore, Maryland, United States
To answer your questions:
1. I think it's good practice to categorize risks as positive and negative, if for no other reason than an inability to identify a risk as one or the other suggests the risk is not well-defined.
2. I don't believe a risk can be both positive and negative, and if it appears so then it likely needs to be better defined.
3. Your example is good.
I'd break down this risk into two separate risks:
Risk 1: Community opposes project (does not want project to be completed)
Risk 2: Community opposes project (wishes to voice concerns that could improve the project) Saving Changes...
I'm a certified PMI Risk Management Professional (PMI-RMP), and I would like to share my understanding of risk in project management drawn from my previous presentation.
Categorizing risk as positive or negative is crucial for identifying opportunities and threats. Positive risks (or opportunities) can enhance project outcomes, while negative risks (or threats) require effective mitigation strategies. This distinction enables teams to prioritize their focus and resources, ultimately leading to more successful project results.
It’s important to note that risks can have both positive and negative aspects simultaneously. For example, heavy rain during a concert might negatively impact the performance and attendance, yet nearby merchandise vendors could benefit from increased umbrella sales.
Here are some common Risk Response Strategies in Project Management for your reference.
Negative Risks:
a) Mitigate : Implementing additional training for staff to reduce the chance of errors in a project.
b) Transfer: Purchasing insurance to cover potential losses from project delays.
c) Avoid: Changing the project schedule to avoid a known conflict with a major holiday.
Positive Risks:
a) Exploit: Allocating extra resources to a high-potential initiative that could lead to early project completion.
b) Share: Partnering with another company to co-develop a feature that could enhance the project’s marketability.
c) Enhance: Investing in improved technology that could boost productivity and reduce overall project costs.
Both Negative and Positive Risks:
a) Accept: Acknowledging that a potential market shift could affect the project but deciding to proceed as planned while monitoring the situation.
b) Escalate: Informing senior management about a new regulatory requirement that could impact the project timeline, seeking their guidance on the best course of action.
There are also other related terms in Project Risk Management that should not be confused, such as Inherent Risk, Residual Risk, Secondary Risk, etc ...