Marcio, I am not sure if I got your question correctly, but I would assume EAP refers to Earnings Allocation Plan.
First, you have to calculate the total duration for all three items which is 897 days then determine the proportional weight for each item (Item Duration/Total Duration) and finally, multiply the proportional weight for each item by 22%.
For example, Item 1: 397/897 = 0.4425 x 22% = 9.72% then items 2 and 3 will be 6.11% each so total is 22%.
Senior Projects Manager | Field & Marten AssociatesNew Westminster, British Columbia, Canada
Marcio, based on the info you provided and what you are looking for, this is the only logical mathematical answer that I can provide. Maybe something is off with your Projectlibre because if you want to get a total of 22%, I can't think of any other way but maybe others can provide better ideas. Saving Changes...