Hi! I'm preparing for PMP test and very confused when why and what EAC formula we suppose to use? Where are three of them, my email: [email protected], Thank you Saving Changes...
Hi,
Estimate at Completion (EAC): This is the current forecast of how much the project is expected to cost. The three formulas are
1. EAC=AC+ETC
2. EAC=BAC/CPI
3. EAC=BAC-VAC
A useful material you can get for PMP Exam preparations is "Project Management with a Focus on the PMP Exam". This is based on the 5th edition of the PMBOK Guide.