What comes first? WBS or Project Charter

linkedin twitter facebook   Work Breakdown Structures (WBS)  
avatar
Bruno Silva Co-Owner| Hoop Porto Alegre, Rs, Brazil
I'm confused about what comes first. I understand that project charter is created in the initiating phase, but this document explicits the budget for the project. But here´s where i get lost: how to determine budget without doing the WBS (that comes before the project charter)? Am i getting things the wrong way?

Thanks for the help!
Sort By:
avatar
Edward Santiago Ny, United States
The Project Charter goes first; it is feed from the Project Statement of Work which you get from the client. From here you create the Project Scope which identifies the deliverables and from here you can create the WBS which decomposes the deliverables in Work Packages and Activities. Need more details let me know.
avatar
Bruno Silva Co-Owner| Hoop Porto Alegre, Rs, Brazil
Thanks for the answer, Edward!

Considering that i´m working on a internal project (not for a client), my boss (that would be the project sponsor) should deliver to me a SOW? There is a need to this on this case?

My question is: if my project charter determines the budget and time for the project, how could i do this in the initiating phase? Some kind of activities planning should be done at this point without being the WBS, right?
avatar
Rebecca Braglio Community Engagement Specialist II| Project Management Institute Newtown Square, Pa, United States
If either of you have any templates you'd be interested in sharing with the community, please let me know - we're in the process of building it up and could use the assistance -- especially in finding out what types of things you decide to include in your WBS and the Project Charter.
avatar
Gaurav Sapra Program Manager| TATA Consultancy Services Edinburgh, Scotland, United Kingdom
Bruno, very relevant and practical question... Generally speaking, my experience has been that we go backwards from the need to project i.e. Business got a need which
- may be worth - high level budget/cost as per Business case of need
- should be fulfilled in what time to be useful for Business
So you got the Budget and Time which if doesn't match your detailed WBS, later in initiation, would need to re-evaluated against Business case..
Rebecca, I should have some charter and, possibly, WBS templates...Happy to share.
avatar
Rebecca Braglio Community Engagement Specialist II| Project Management Institute Newtown Square, Pa, United States
Gaurav -

awesome! sending you a message now....Thanks!
avatar
Yolanda Criddle Tacoma, Wa, United States
Hello everyone, I'm new here . Is there a chat on here where I can met new PM and ask questions?

Thanks
avatar
Antonella Bojanich Project Manager| Northwell Health Prt Washingtn, Ny, United States
Great question Bruno, having the same issues. To all who responded thank you for clarifying.