Q.1 The correct answer is:
B) Perform a variance analysis to identify the root causes of the delays and cost overruns.
Explanation:
When a project falls behind schedule and goes over budget, the first step is understanding the root causes of these issues. Performing a variance analysis allows the project manager to compare actual performance against the planned schedule and budget, identifying where things went wrong.
Once the issues are identified:
The project manager can determine if corrective or preventive actions are needed.
Based on the findings, a recovery plan can be developed if necessary (option A).
Re-baselining (option D) or negotiating with stakeholders (option C) should only be considered after understanding the variance and exploring all recovery options.
This approach aligns with best practices in project management, such as continuous monitoring and controlling to manage project constraints effectively.