Project Management

Project Management Central

Please login or join to subscribe to this thread

Topics: Scheduling
new to scheduling in microsoft project please help!
avatar
oli b project manager| None Leeds, United Kingdom
Does anyone know what is the right way to do this in microsoft project professional; if my engineer can complete 1.5 vans per day, taking account of holidays, how can I calculate when they will have finished 150 vans? There must be an elegant way to do this that will be responsive to my increasing engineer resource etc.?
Sort By:
avatar
Kiron Bondale
Community Champion
Retired | Mentor Welland, Ontario, Canada
As far as I know, MSP does not support the ability to put in a productivity or throughput value for a work-type resource such that duration & work can be calculated. For any task you have to provide either the duration or the work (effort).

In this case, the work is 100 days and the duration would be calculated by MSP based on the engineer's resource calendar. If you modify the engineer's availability or increase the number of engineers assigned, the duration would change if the task is an effort driven task.

Kiron
avatar
Svenja Merle
Community Champion
Kassel, Germany
Hi Oli,
you might find support at Microsoft directly - there is the option du schedule task "effort-driven". So you might be able to integrate the productivity:
https://support.microsoft.com/en-us/office...#__toc312058389

Please login or join to reply

Content ID:
ADVERTISEMENTS

"You must be the change you want to see in the world."

- Mahatma Gandhi

ADVERTISEMENT

Sponsors