Project Management

Please login or join to subscribe to this thread

Questions about the PMP Practice Exam

linkedin twitter facebook  
avatar
Shuhei Miyazaki Nerima-Ku, 13, Japan
I am not satisfied with the answers to the Practice Exam. Please help me.

#Mini Exam 9: People Domain Issue #3.
Midway through a project, the project manager identifies new stakeholders. Each of these new stakeholders plays a different project role.What should the project manager do first?
A.Meet with the project sponsor to learn if new roles have been created.
B.Review the stakeholder register.
C.Submit a change request to the change control board (CCB).
D.Update the stakeholder management plan.

The answer is D, but I feel that B is first.
You should first update the stakeholder register and then update the stakeholder management plan.

#Mini Exam 9: People Domain Issue #6.

Team members express frustration because their functional manager does not listen to their opinions. They seem reluctant to devote themselves to the remainder of the project.
What should the project manager do?

A.Demonstrate support for the team by discussing their goals and beliefs.
B.Break the remaining work into smaller tasks and divide the tasks among the team.
C.Ask the team to prioritize the tasks remaining in the project.
D.Discuss the team's concerns with the functional manager.

The answer is A, but I feel that D is appropriate.
Discussing the team's goals and beliefs does not solve the problem of the functional manager not listening to the team members. It is best to speak directly with the functional manager.

#Mini Exam 9: People Domain Issue #13.

During project initiation, the project manager learns that a key stakeholder will leave the project for a month to consult on another strategic project.
What should the project manager do first?

A.Update the issue log and notify the other stakeholders.
B.Ask the functional manager to provide a replacement while the stakeholder is unavailable.
C.Interview the stakeholder to gather relevant information and expert judgment.
D.Update the risk management plan to include the impact of the stakeholder's absence.

The answer is A, but I feel that C is appropriate.
First the impact of the key stakeholder leaving the project for a month should be investigated.
The issue log should be updated and other stakeholders notified after that.
Sort By:
< 1 2 >
avatar
Shuhei Miyazaki Nerima-Ku, 13, Japan
I need help with the following as well.

#Mini Exam 12: Hybrid Issue #15.

The project manager's company won a digital transformation project request for proposal (RFP) with clear scope, time and cost. As part of the RFP clause, the project manager's company also provided the number of resources required to complete the project. This is a very high investment project, and the customer wants to monitor the progress regularly.



Since it is a fixed price project, what approach should the project manager use?


A.Use a predictive approach and send the daily status report to the customer.
B.Use an Agile approach and showcase each successful completion of the story.
C.Use a hybrid approach and showcase each successful completion of each module.
D.Use a predictive approach and showcase each successful completion of each module.

The answer is C, but I don't understand.
I recognize that a predictive approach is valid for projects where scope, cost, and time are clear.
If the hybrid approach is more appropriate even for projects with clear scope, cost, and time, then what exactly would be a project for which the predictive approach would be more appropriate?
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Shuhei -

Could you clarify which practice exam this is as different practice exams do vary widely in terms of quality?

The hybrid question is especially poorly written so I would question the overall quality of this exam if that question is representative of the level of the rest...

Kiron
avatar
Shuhei Miyazaki Nerima-Ku, 13, Japan
KIron -
Appreciate your reply.
I am asking about the Mini Exam in the Practice Exams offered by “PMI Study Hall PMP Essentials”.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Shuhei

Mini Exam 9 - Issue #3: I agree with you in that the correct answer should be B. When new stakeholders are identified, the first thing the project manager should do is review the stakeholder register. This document contains information on all identified stakeholders, their roles, interests, and the level of influence they have on the project. By reviewing it, the project manager can ensure that these new stakeholders are properly included in the register, with their roles and responsibilities clearly defined. Once the register is updated, the project manager can proceed with the rest of the actions.

Mini Exam 9 - Issue #6: I also agree with you. I would chose D as the correct answer because while demonstrating support and engaging with the team is important (Answer A), this option does not directly address the core issue: the functional manager not listening to the team. This could help the team feel better in the short term but may not resolve the root cause of the frustration.

Mini Exam 9 - Issue #13: I would chose D as the correct answer as well because when a key stakeholder is going to be absent for a month, the project manager’s first priority should be to gather as much relevant information and expert judgment from the stakeholder before they leave. This ensures that the project has the necessary knowledge and insights to continue without interruption during their absence. I don't believe option A is the correct answer because the issue log is typically used for tracking problems that have already occurred, not for proactively managing planned absences.

Mini Exam 12 - Issue #15: I agree with Kiron, the question is weak. A hybrid approach might work in some cases, but in a fixed-price project with clear, defined scope, a purely predictive approach is often more appropriate. A hybrid approach would typically be used if there is an evolving or unclear scope that requires more flexibility, which isn't the case here so I would chose Option A.

Hope this helps! 
avatar
Shuhei Miyazaki Nerima-Ku, 13, Japan
Rami -
I appreciate your response.
I am relieved that my thoughts on PMP Exam seem to be correct.
However, I think the low level of the PMI-approved PMP practice exam will be a problem for many learners.
...
1 reply by Rami Kaibni
Nov 07, 2024 1:33 PM
Rami Kaibni
...

Shuhei, if those exams are from PMI Study Hall, that could be an issue. They might have a specific rationale for why their answers are considered correct. Do they provide explanations for the answers?

I agree with most of your thoughts, but the challenge is that those who create the exam questions may approach things from a different perspective. That's why understanding the rationale behind the answers is so important—it helps clarify why one choice is correct over the others.

A resource I highly recommend for simulation exams is PM PrepCast. They offer a robust question bank and provide detailed rationales for each answer, which is invaluable for understanding the why, how, when, and what behind each question.

Good Luck!

avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Nov 07, 2024 12:10 AM
Replying to Shuhei Miyazaki
...
Rami -
I appreciate your response.
I am relieved that my thoughts on PMP Exam seem to be correct.
However, I think the low level of the PMI-approved PMP practice exam will be a problem for many learners.

Shuhei, if those exams are from PMI Study Hall, that could be an issue. They might have a specific rationale for why their answers are considered correct. Do they provide explanations for the answers?

I agree with most of your thoughts, but the challenge is that those who create the exam questions may approach things from a different perspective. That's why understanding the rationale behind the answers is so important—it helps clarify why one choice is correct over the others.

A resource I highly recommend for simulation exams is PM PrepCast. They offer a robust question bank and provide detailed rationales for each answer, which is invaluable for understanding the why, how, when, and what behind each question.

Good Luck!

...
1 reply by Shuhei Miyazaki
Nov 08, 2024 5:32 AM
Shuhei Miyazaki
...
Rami - 
Thank you for your response.
These are the practice exams provided by "PMI Study Hall PMP Essentials".
The explanations were provided, but they did not convince me.
I will make sure I understand the rationale before taking the real exam.
avatar
Danny PMP, PgMP
Community Champion
Senior Consultant Tokyo, Japan

Dear Shuhei,

In Project Risk Management, it is important to first identify and analyze the issues or risks, and then respond accordingly.

I could be wrong, but these are my thoughts:


#Mini Exam 9: People Domain Issue #3.

Midway through a project, the project manager identifies new stakeholders. Each of these new stakeholders plays a different project role.What should the project manager do first?

A. Meet with the project sponsor to learn if new roles have been created.
B. Review the stakeholder register.
C. Submit a change request to the change control board (CCB).
D. Update the stakeholder management plan.

My Answer : B (I have a different opinion than the standard answer.)

Explanation:
The project manager identifies new stakeholders, thus the next step is to review (& maybe update) the stakeholder register, and confirm whether the stakeholders is included in the stakeholder register, before we proceed to update (change) the stakeholder management plan.


#Mini Exam 9: People Domain Issue #6

Team members express frustration because their functional manager does not listen to their opinions. They seem reluctant to devote themselves to the remainder of the project.

What should the project manager do?

A. Demonstrate support for the team by discussing their goals and beliefs.
B. Break the remaining work into smaller tasks and divide the tasks among the team.
C. Ask the team to prioritize the tasks remaining in the project.
D. Discuss the team's concerns with the functional manager.

My Answer : A

Explanation:
While D (Discuss the team’s concerns with the functional manager) seems like it might be a valid approach, A (Demonstrate support for the team by discussing the project related goals and their beliefs). The project manager needs to address the team’s frustrations and demonstrate that their concerns are heard. By understanding their goals and beliefs, the project manager can improve the team’s morale, foster trust, and address underlying issues. Once the project manager has provided emotional support to the team, they can then discuss the team’s concerns with the functional manager. Directly addressing the functional manager before dealing with the team’s concerns may not help the team’s immediate frustration. The project manager’s role is to maintain team cohesion and motivation, and answer "A" helps build that foundation before tackling external issues like management problems.


#Mini Exam 9: People Domain Issue #13.

During project initiation, the project manager learns that a key stakeholder will leave the project for a month to consult on another strategic project.
What should the project manager do first?

A. Update the issue log and notify the other stakeholders.
B. Ask the functional manager to provide a replacement while the stakeholder is unavailable.
C. Interview the stakeholder to gather relevant information and expert judgment.
D. Update the risk management plan to include the impact of the stakeholder's absence.

My Answer: A

Explanation:
The issue log is a tool used to track issues as they arise during the project. The absence of a key stakeholder is a potential issue that should be recorded as soon as it's known. Whenever there are issues in the project, updating the issue log is the first step to helps document the situation, and the project manager can take the next steps based on this. Once the issue is logged, the project manager should communicate this to other stakeholders so they are aware of the potential gap. This transparency ensures that all involved parties are aligned. While it is critical to gather information from the stakeholder, the first priority is to log and communicate the issue. Interviewing the stakeholder should happen after documenting the issue and informing others. Risk Management Plan (D) may come later as well, but first, the project manager needs to understand the immediate implications (thus logging it) before moving to update the risk management plan.


#Mini Exam 12: Hybrid Issue #15.

The project manager's company won a digital transformation project request for proposal (RFP) with clear scope, time and cost. As part of the RFP clause, the project manager's company also provided the number of resources required to complete the project. This is a very high investment project, and the customer wants to monitor the progress regularly.
Since it is a fixed price project, what approach should the project manager use?

A. Use a predictive approach and send the daily status report to the customer.
B. Use an Agile approach and showcase each successful completion of the story.
C. Use a hybrid approach and showcase each successful completion of each module.
D. Use a predictive approach and showcase each successful completion of each module.

My Answer: C

Explanation:
The correct answer is C (Hybrid approach) because the project involves a fixed-price contract with clear scope, time, and cost, but the customer wants regular progress updates. A hybrid approach combines the structured, predictive methodology for planning and overall project management with more flexible, iterative elements, like showcasing each completed module. This allows the project manager to deliver progress in manageable increments while adhering to the overall fixed parameters of scope, cost, and time, making it more suitable for large, complex projects such as digital transformation.

...
1 reply by Rami Kaibni
Nov 07, 2024 10:26 PM
Rami Kaibni
...
Shuhei, this is a good example of an answer that makes sense, but from our perspective, it's a bit different. In project management, there are often multiple valid approaches. However, for the purposes of the exam, it's important to adopt the mindset of the exam writers.

Danny, for the first question, your explanation is consistent with Answer B, not D as the next step is Reviewing Stakeholder Register, unless I am missing something. Your answers for the rest of the questions make sense to me, even though we have different point of views.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Nov 07, 2024 9:35 PM
Replying to Danny PMP, PgMP
...

Dear Shuhei,

In Project Risk Management, it is important to first identify and analyze the issues or risks, and then respond accordingly.

I could be wrong, but these are my thoughts:


#Mini Exam 9: People Domain Issue #3.

Midway through a project, the project manager identifies new stakeholders. Each of these new stakeholders plays a different project role.What should the project manager do first?

A. Meet with the project sponsor to learn if new roles have been created.
B. Review the stakeholder register.
C. Submit a change request to the change control board (CCB).
D. Update the stakeholder management plan.

My Answer : B (I have a different opinion than the standard answer.)

Explanation:
The project manager identifies new stakeholders, thus the next step is to review (& maybe update) the stakeholder register, and confirm whether the stakeholders is included in the stakeholder register, before we proceed to update (change) the stakeholder management plan.


#Mini Exam 9: People Domain Issue #6

Team members express frustration because their functional manager does not listen to their opinions. They seem reluctant to devote themselves to the remainder of the project.

What should the project manager do?

A. Demonstrate support for the team by discussing their goals and beliefs.
B. Break the remaining work into smaller tasks and divide the tasks among the team.
C. Ask the team to prioritize the tasks remaining in the project.
D. Discuss the team's concerns with the functional manager.

My Answer : A

Explanation:
While D (Discuss the team’s concerns with the functional manager) seems like it might be a valid approach, A (Demonstrate support for the team by discussing the project related goals and their beliefs). The project manager needs to address the team’s frustrations and demonstrate that their concerns are heard. By understanding their goals and beliefs, the project manager can improve the team’s morale, foster trust, and address underlying issues. Once the project manager has provided emotional support to the team, they can then discuss the team’s concerns with the functional manager. Directly addressing the functional manager before dealing with the team’s concerns may not help the team’s immediate frustration. The project manager’s role is to maintain team cohesion and motivation, and answer "A" helps build that foundation before tackling external issues like management problems.


#Mini Exam 9: People Domain Issue #13.

During project initiation, the project manager learns that a key stakeholder will leave the project for a month to consult on another strategic project.
What should the project manager do first?

A. Update the issue log and notify the other stakeholders.
B. Ask the functional manager to provide a replacement while the stakeholder is unavailable.
C. Interview the stakeholder to gather relevant information and expert judgment.
D. Update the risk management plan to include the impact of the stakeholder's absence.

My Answer: A

Explanation:
The issue log is a tool used to track issues as they arise during the project. The absence of a key stakeholder is a potential issue that should be recorded as soon as it's known. Whenever there are issues in the project, updating the issue log is the first step to helps document the situation, and the project manager can take the next steps based on this. Once the issue is logged, the project manager should communicate this to other stakeholders so they are aware of the potential gap. This transparency ensures that all involved parties are aligned. While it is critical to gather information from the stakeholder, the first priority is to log and communicate the issue. Interviewing the stakeholder should happen after documenting the issue and informing others. Risk Management Plan (D) may come later as well, but first, the project manager needs to understand the immediate implications (thus logging it) before moving to update the risk management plan.


#Mini Exam 12: Hybrid Issue #15.

The project manager's company won a digital transformation project request for proposal (RFP) with clear scope, time and cost. As part of the RFP clause, the project manager's company also provided the number of resources required to complete the project. This is a very high investment project, and the customer wants to monitor the progress regularly.
Since it is a fixed price project, what approach should the project manager use?

A. Use a predictive approach and send the daily status report to the customer.
B. Use an Agile approach and showcase each successful completion of the story.
C. Use a hybrid approach and showcase each successful completion of each module.
D. Use a predictive approach and showcase each successful completion of each module.

My Answer: C

Explanation:
The correct answer is C (Hybrid approach) because the project involves a fixed-price contract with clear scope, time, and cost, but the customer wants regular progress updates. A hybrid approach combines the structured, predictive methodology for planning and overall project management with more flexible, iterative elements, like showcasing each completed module. This allows the project manager to deliver progress in manageable increments while adhering to the overall fixed parameters of scope, cost, and time, making it more suitable for large, complex projects such as digital transformation.

Shuhei, this is a good example of an answer that makes sense, but from our perspective, it's a bit different. In project management, there are often multiple valid approaches. However, for the purposes of the exam, it's important to adopt the mindset of the exam writers.

Danny, for the first question, your explanation is consistent with Answer B, not D as the next step is Reviewing Stakeholder Register, unless I am missing something. Your answers for the rest of the questions make sense to me, even though we have different point of views.
...
1 reply by Danny PMP, PgMP
Nov 07, 2024 10:51 PM
Danny PMP, PgMP
...

Thank you very much Rami Kaibni for corrections. I have amended the mistake.

The site story:
#Mini Exam 9: People Domain Issue #6, is a real example of something I am currently experiencing.

In project management, there is no "perfect" answer to every challenge. In reality, the best solution is one that fits the situation and addresses the issues effectively. However, it is still essential to understand the "best practices," which represent the collective wisdom of experienced experts. These best practices serve as a guide to help us make informed decisions. This highlights the importance of certifications, as they validate our understanding of these practices, rather than relying solely on our limited experience or knowledge.

Meanwhile, as the famous Chinese proverb goes, "It doesn't matter whether the cat is black or white, as long as it catches the mouse." This emphasizes that what truly matters is the outcome, not necessarily the method, as long as it achieves the desired result.

avatar
Danny PMP, PgMP
Community Champion
Senior Consultant Tokyo, Japan
Nov 07, 2024 10:26 PM
Replying to Rami Kaibni
...
Shuhei, this is a good example of an answer that makes sense, but from our perspective, it's a bit different. In project management, there are often multiple valid approaches. However, for the purposes of the exam, it's important to adopt the mindset of the exam writers.

Danny, for the first question, your explanation is consistent with Answer B, not D as the next step is Reviewing Stakeholder Register, unless I am missing something. Your answers for the rest of the questions make sense to me, even though we have different point of views.

Thank you very much Rami Kaibni for corrections. I have amended the mistake.

The site story:
#Mini Exam 9: People Domain Issue #6, is a real example of something I am currently experiencing.

In project management, there is no "perfect" answer to every challenge. In reality, the best solution is one that fits the situation and addresses the issues effectively. However, it is still essential to understand the "best practices," which represent the collective wisdom of experienced experts. These best practices serve as a guide to help us make informed decisions. This highlights the importance of certifications, as they validate our understanding of these practices, rather than relying solely on our limited experience or knowledge.

Meanwhile, as the famous Chinese proverb goes, "It doesn't matter whether the cat is black or white, as long as it catches the mouse." This emphasizes that what truly matters is the outcome, not necessarily the method, as long as it achieves the desired result.

...
1 reply by Shuhei Miyazaki
Nov 08, 2024 6:00 AM
Shuhei Miyazaki
...
Danny -
Thank you for your response.
I am struggling with the PMP issues because many of them are complex and ambiguous, but I will do my best to become a PMP holder.
ありがとうございます。
avatar
Shuhei Miyazaki Nerima-Ku, 13, Japan
Nov 07, 2024 1:33 PM
Replying to Rami Kaibni
...

Shuhei, if those exams are from PMI Study Hall, that could be an issue. They might have a specific rationale for why their answers are considered correct. Do they provide explanations for the answers?

I agree with most of your thoughts, but the challenge is that those who create the exam questions may approach things from a different perspective. That's why understanding the rationale behind the answers is so important—it helps clarify why one choice is correct over the others.

A resource I highly recommend for simulation exams is PM PrepCast. They offer a robust question bank and provide detailed rationales for each answer, which is invaluable for understanding the why, how, when, and what behind each question.

Good Luck!

Rami - 
Thank you for your response.
These are the practice exams provided by "PMI Study Hall PMP Essentials".
The explanations were provided, but they did not convince me.
I will make sure I understand the rationale before taking the real exam.
< 1 2 >

Please login or join to reply

Content ID:
ADVERTISEMENTS

"When you cannot get a compliment any other way, pay yourself one."

- Mark Twain

ADVERTISEMENT

Sponsors